CPI(M) cadres protest incomplete road work in Tiruvottiyur

November 12, 2013 09:01 am | Updated 09:01 am IST - CHENNAI:

Widening work on Tiruvottiyur High Road has been going on for seven years and is still not finished. Photo: B. Jothi Ramalingam

Widening work on Tiruvottiyur High Road has been going on for seven years and is still not finished. Photo: B. Jothi Ramalingam

The Communist Party of India (Marxist) staged a protest in Tiruvottiyur on Monday, demanding the completion of widening work on Tiruvottiyur High Road. The work has been going on for seven years now.

The protest was staged in front of the Tiruvottiyur zonal office of the Chennai Corporation.

The protestors also demanded the completion of various projects including the construction of an underground drainage network, laying of drinking water pipelines and improvement of interior roads.

R. Jayaraman, secretary of the Tiruvottiyur-Ennore area committee of the CPI (M) said that residents have been put to untold misery due to the inordinate delay in completing the work.

“Transformers and EB poles have not yet been shifted and debris from shops that were demolished several months ago still remains on the road side. The Highways Department has taken seven years to widen a 5-kilometre stretch and will continue to take more time,” he said.

Both residents and shopkeepers have been affected by this widening project. J. Ganeshkumar who runs a shop in Therady, said that he had demolished his shop twice during various stages of the widening.

“Initially, officials said the road would be 60 feet wide. Then they changed it to 66 feet. Now the government has said that if we get Metro Rail, they will require 100 feet. But if that is done, almost all the shops on this road will vanish,” he said.

Officials of the Highways Department said the widening work will be completed by the end of March next year. Out of the five kilometres the project encompasses, stormwater drain work was being carried out over 2 km. Tenders are to be called for the construction of the remaining length of stormwater drains.

Work orders for Rs. 20 lakh have been issued to a contractor to carry out repair work. The delay was due to various factors including lack of interest among contractors to take up the project initially, land acquisition and shifting of utilities, an official explained.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.