Namma Metro Phase I at double the cost and double the time

From an estimated cost of ₹6,500 crore when work began in 2006, the final bill for Phase I has come to ₹14,405 crore

June 16, 2017 09:33 pm | Updated 09:33 pm IST

After a delay of over five years and double the estimated cost, Phase I of Namma Metro is all set to be completely operationalised on Saturday with the inauguration of the Green Line by President Pranab Mukherjee. The opening of the Green Line also brings the metro convenience to the southern parts of the city.

The 42.3 km Phase I of the project with two corridors – East-West (Purple Line) and North-South (Green Line) – was estimated to cost ₹6,500 crore when work began in 2006 and was set to be completed in 2011. However, as Phase I gets completely operational, the final bill has come to ₹14,405 crore.

Transport experts and traffic police are hoping that completion of Phase I will be a game changer for the city. “For the first time, Namma Metro will become an end-to-end commute option, which we hope will reduce congestion on the roads,” said R. Hitendra, Additional Commissioner of Police (Traffic).

Namma Metro ridership, which is pegged at an average of 1.75 lakh per day, is expected to rise to 5 lakh, BMRCL officials said.

But is Namma Metro prepared to handle that kind of rider volume? Namma Metro trains may continue to run packed till the middle of next year, as the order that BMRCL has placed for additional coaches is expected to be delivered by June 2018. BMRCL has come under sharp criticism for the delay in placing orders for additional coaches.

Your metro ride set to get dearer

The completion of Phase I comes with a bad news for commuters. Your ride is set to get dearer, starting Saturday.

Pradeep Singh Kharola, Managing Director, BMRCL confirmed a fare hike of around 10% and said that the new fare chart would be announced on Saturday. This will be the first ever fare hike of Namma Metro since the first line between M.G. Road and Baiyappanahalli became operational in 2011.

Sources in BMRCL said that the hike is being effected to reduce cash loss in operational costs. Sources said that BMRCL has till date incurred a loss of ₹276 crore in operational costs.

However, even with the hike, Namma Metro will be far away from breaking even, sources said. Officials said that while 10% is the proposed hike, ticket prices have been rounded off to prevent a scramble for change at the counters.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.