Jayanagar complex remains an unwanted child

BDA wants to wash its hands off the ambitious project, but BBMP is not willing to take back its property

July 18, 2018 10:12 pm | Updated 10:12 pm IST

 The new block at Jayanagar 4th block, which was built after demolishing the Puttanna Kanagal theatre.

The new block at Jayanagar 4th block, which was built after demolishing the Puttanna Kanagal theatre.

Ten years after a fire ravaged a part of the Jayanagar shopping complex, its grand redevelopment plans have been reduced to a ₹57 crore bill and six floors of emptiness.

The nearly 45-year-old structure located in the heart of Jayanagar is owned by the Bruhat Bengaluru Mahanagara Palike (BBMP). The Bangalore Development Authority (BDA) was to re-develop the property, but wants to wash its hands off the project after constructing just one of the four towers that were proposed.

The stalemate has resulted in the newly-constructed block remaining empty.

The original plan envisaged razing the shopping complex, including the Puttana Kanagal theatre, to make way for four swanky towers that would include a multiplex, multi-level parking and a commercial complex. In October 2010, the property was handed over to the BDA for redevelopment.

A few years later, the BDA demolished the Puttanna Kanagal theatre and constructed one block, under the first phase of the project at a cost of ₹57 crore. The new block (basement parking, G+6) was inaugurated last October by the then chief minister Siddaramaiah. However, the block yet to be occupied. Meanwhile, the BDA decided to hand over the project and the property back to the BBMP.

Ravikrishna Reddy from the Lanchamukta Karnataka Nirmana Vedike claimed that government agencies lose nearly ₹2 lakh in rental revenue every day. “The vedike filed a case with the Lokayukta. But since there was no progress, we decided to withdraw the case,” he said.

In an order dated October 10, 2017, Lokayukta P. Vishwanatha Shetty directed the BBMP to take possession of the existing property, vacate tenants / leasees from the old building, rehabilitate them in the new block after fixing a reasonable rent, apart from submitting a status report within two months.

Stuck in a limbo, the ambitious project has disintegrated into a mess.

“There is no proper parking facility or space for pedestrians,” said N.S. Mukunda, founder of Citizens' Action Forum. He suggested that the BBMP form a committee, including zonal officials and local citizens, to monitor the project, which could restore the complex to its former glory.

The subject has been raised twice in the council, but was deferred both times. This is because BDA wants the civic body to foot the ₹57 crore bill for construction of the new block.

“The council will have to decide. We will be placing the subject once again during this month's council meeting,” said BBMP Commissioner N. Manjunath Prasad.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.