First-of-its-kind underground transformer inaugurated in Bengaluru’s Malleswaram

Besides freeing up space on footpaths and making them safer for pedestrians, underground transformer system will safeguard equipment from storms and variations in ambient temperature, thereby improving reliability of the system

September 05, 2023 02:58 pm | Updated 09:36 pm IST - bengaluru

A 500-kVA underground transformer has been fixed by Bescom under the footpath of 15th Cross Road in Malleswaram, in Bengaluru. It was inaugurated on September 5, 2023.

A 500-kVA underground transformer has been fixed by Bescom under the footpath of 15th Cross Road in Malleswaram, in Bengaluru. It was inaugurated on September 5, 2023. | Photo Credit: K. Murali Kumar

The next time you are walking on the 15th Cross Road in Malleswaram and stumble upon a concrete platform on the footpath, you might be walking above a fully functional electric transformer. Claimed to be the first-of-its-kind in India, Bangalore Electricity Supply Company (Bescom) and Bruhat Bengaluru Mahanagara Palike (BBMP) have installed a 500 KV underground distribution transformer, which was inaugurated on September 5. 

First In India — Bengaluru takes electricity transformer underground | Video Credit: K Murali Kumar

Standing on the 30 mm concrete structure built at ground level, it is difficult to guess that a high technology distribution transformer is busy at work underneath. The transformer is placed 10 feet below the ground. At the ground level, you can see a metal door, which resembles a water sump door. Opening this door reveals a ladder, which gives access to a 480 square feet room that houses the transformer.

The transformer is placed 10 feet below the ground. At the ground level, you can see a metal door, which resembles a water sump door. Opening this door reveals a ladder, which gives access to a 480 square feet room that houses the transformer.

The transformer is placed 10 feet below the ground. At the ground level, you can see a metal door, which resembles a water sump door. Opening this door reveals a ladder, which gives access to a 480 square feet room that houses the transformer. | Photo Credit: K. Murali Kumar

This project is the outcome of an initiative to make footpaths safer for pedestrians. Earlier, the transformer had been fixed on the footpath and was posing a threat to pedestrians

The total cost of the project was ₹1.97 crore with Bescom contributing ₹1.33 crore, which includes installing a 500 KV dry type transformer, 8-way solid RMU, 5-way LT distribution panel, 2 KV UPS, 1 HP submersible water pump, lighting and air ventilation system, and temperature and humidity monitoring system. BBMP contributed ₹64 lakh for the civil work. The project was completed in 365 days, according to an official of Bescom. 

Mahantesh Bilagi, Managing Director, Bescom explained that the underground transformer system will help in safeguarding electrical equipment from experiencing severe climatic conditions, including storms and high ambient temperature, thereby improving the reliability and life of the operation.  

Have the transformer underground will help in safeguarding electrical equipment from storms and variations in ambient temperature, thereby improving the reliability and life of the system.

Have the transformer underground will help in safeguarding electrical equipment from storms and variations in ambient temperature, thereby improving the reliability and life of the system. | Photo Credit: K. Murali Kumar

K. J. George, Minister of Energy, who inaugurated the facility, said that more such projects will be taken up in Bengaluru. “While we have already identified transformers that are posing a hazard, steps are being taken to relocate them. After studying the feasibility report submitted by Bescom, we will look at more locations to install transformers underground,” he said. 

While Bescom has already taken up the work of converting overhead high tension (HT) lines to underground cables in a phased manner, future plans include taking its distribution transformers, Ring Main Units (RMU), feeder pillar boxes and other equipment underground. Apart from avoiding electric accidents, this move is also expected to cut down distribution losses and ensure supply of good quality electricity.  

BBMP Chief Civic Commissioner Tushar Giri Nath said that when such underground projects are taken up in future, measures will be taken to ensure that the concrete ceiling overhead is aligned with the footpath for the convenience of pedestrians.

Top News Today

Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.