Uppur project on fast track

BHEL completes more than 50% of piling works

Put on the fast track, works in the 2x800 MW Uppur supercritical thermal power plant has gained momentum with Bharat Heavy Electricals Limited (BHEL) completing more than 50% of piling works and Tamil Nadu generation and distribution corporation (Tangedco) opening its site office for close coordination.

Tangedco, the executing agency, fighting a legal battle to secure the remaining 359 acres of patta lands, has paved way for the three contractors – the BHEL, Reliance Infrastructure Limited and Larson and Toubro to continue their works unhindered. “We have speeded up the work and it is going on in full swing,” Tangedco officials said.

The ₹12,655 crore power project would be boon to this backward district, they said. BHEL, which was entrusted with the major task of establishing Boiler, Turbine and Generators (BTG), has started bringing in machineries such as stators and electro static precipitators. It has already completed more than 50% of the 6,000 odd pilings, each measuring to the depth of 14 to 22 meters and started fabrication works and power home structures, they said. The Reliance Infrastructure Limited which has won the balance of project contract has commenced the preliminary and enabling works and this was expected to speed up after Tangedco resolved the legal wrangles and handed over the 359 acres of patta lands, they said.

The L&T which was awarded the ‘sea water intake and outfall system’ has completed the enabling work and was presently carrying out pipeline fabrication work, slab and high girder casting work, officials said. Tangedco has taken possession of 229.59 acres of government land and 408 acres of private patta lands.

The Madras High Court after completing hearings, reserved orders in the case relating to the acquisition of 359 acres of patta lands for the project.

A letter from the Editor


Dear reader,

We have been keeping you up-to-date with information on the developments in India and the world that have a bearing on our health and wellbeing, our lives and livelihoods, during these difficult times. To enable wide dissemination of news that is in public interest, we have increased the number of articles that can be read free, and extended free trial periods. However, we have a request for those who can afford to subscribe: please do. As we fight disinformation and misinformation, and keep apace with the happenings, we need to commit greater resources to news gathering operations. We promise to deliver quality journalism that stays away from vested interest and political propaganda.

Support Quality Journalism
Recommended for you
This article is closed for comments.
Please Email the Editor

Printable version | Jun 6, 2020 7:36:19 AM | https://www.thehindu.com/news/cities/Tiruchirapalli/uppur-project-on-fast-track/article26159380.ece

Next Story