After 9 months, a road trip from Maharashtra ends

Tractor trailer transporting 70-tonne ISRO equipment covered about 5 km a day

July 18, 2020 08:12 pm | Updated 11:39 pm IST - THIRUVANANTHAPURAM

A tractor trailer transporting an autoclave for the VSSC’s Vattiyurkavu campus passes by the city on Saturday.

A tractor trailer transporting an autoclave for the VSSC’s Vattiyurkavu campus passes by the city on Saturday.

It wouldn’t be much of an exaggeration if you were to call it the slowest motorised vehicle on Indian roads in the past one year.

A heavy-duty tractor trailer transporting a 70-tonne industrial autoclave for the Composites Entity (CMSE) of ISRO’s Vikram Sarabhai Space Centre (VSSC) at Vattiyurkavu finally entered the capital city on Saturday.

This is the last leg of an epic journey for the rig which left Ambarnath, Maharashtra, in September last year. It is expected to end its assignment on the VSSC’s Vattiyurkavu campus on Sunday.

Across four States

The massive size of the trailer and the sheer weight of its cargo meant that for much of its interesting journey across four States, the vehicle proceeded at an unhurried pace of about 5 km per day. At many places along the route, tree branches had to be trimmed and overhead electric lines shifted so that it could pass unhindered.

Its purpose

Industrial autoclaves are pressurised vessels used in the manufacture of advanced composites, notably for the aerospace industry. In ISRO’s case, this piece of cylindrical machinery would enable easier and cost-effective manufacture of very large and light-weight structures needed to launch vehicles and satellites, a VSSC official said.

Its dimensions

The autoclave, which has a diameter of five metres and length of six metres, was manufactured by Unique Chemoplant Equipments, Nasik, at its Ambarnath factory and costs ₹9 crore, including transportation charges. The VSSC does have autoclaves, but none this large.

Time for installation

On Saturday, the massive vehicle passed through Karamana and Killipalam and reached Museum. Once it reaches Vattiyurkavu, it would take another three months before it is installed, integrated with the electrical systems and controls and commissioned.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.