Shiradi Ghat work may be completed in 10 days, says Mahadevappa

And this could happen if it does not rain, he says

June 07, 2015 12:00 am | Updated 05:39 am IST - MANGALURU:

Unexpected downpour in April-May affected the progress of the work on the Shiradi Ghat.— File Photo

Unexpected downpour in April-May affected the progress of the work on the Shiradi Ghat.— File Photo

Minister for Public Works H.C. Mahadevappa on Saturday said the concreting of the 13-km stretch of Shiradi Ghat would be completed in about 10 days if it does not rain. Unexpected downpour for 21 days in April-May affected severely the progress of the work, he said. Speaking at the foundation-laying ceremony of improving the approach road to district court complex here, Mr. Mahadevappa said the government did not want to compromise with the quality of work.

Though the completion period was 18 months, the contractor had agreed to do the work within six months. However, the rain played the spoilsport, the Minister said. Though Shiradi Ghat, the lifeline of the State, has been in bad shape for years, Oscar Fernandes, as the then Union Minister for Road Transport and Highways, sanctioned concreting work, Mr. Mahadevappa noted.

Of the 13-km stretch between Heggere and Kempuhole taken up for concreting in Package 1 at a cost of Rs. 70 crore, the 8-km stretch has fully been concreted by now. Concrete has also been laid for another 2 km on one half of the road. About 2 km of the road comprising 12 curves, that had been concreted two years ago, is not being touched; but is being strengthened and widened, Mr. Mahadevappa said.

The Minister said technical evaluation of bids is under progress for the second package of improving Shiradi Ghat. The package includes concreting another 13-km stretch between Kempuhole and Adda Hole (Gundia), and relaying bitumen between Marenahlli and Gulagalale (21 km).

Alternative roads

The department approved a plan to improve the 12-km stretch of Shishila-Byrapura road as an alternative to Shiradi Ghat. While Shishila is in Belthangadi Taluk, Byrapura is in Mudigere Taluk. Work on improving Bisile Ghat connecting Sakaleshapura and Kukke Subrahmanya too has been approved to be taken up at a cost of Rs. 24 crore, Mr. Mahadevappa said. The Charmadi Ghat is being widened and strengthened, he added.

Rajya Sabha Member Oscar Fernandes, Minister for Forests, Environment and Ecology B. Ramanath Rai, Mangaluru South MLA J.R. Lobo, MLC Ivan D’Souza, Mayor Jasinta Vijaya Alfred, Principal District and Sessions Judge M.G. Uma and others were present.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.