Maravoor Bridge to be thrown open to traffic today

PWD successfully conducts load test on the restored slab

July 29, 2021 08:28 pm | Updated July 30, 2021 12:26 am IST - MANGALURU

Public Works Department engineers conducting load test on the restored Maravoor Bridge across the Phalguni on Airport Road in Mangaluru on Thursday after restoring one of the slabs that had sunken on June 15.

Public Works Department engineers conducting load test on the restored Maravoor Bridge across the Phalguni on Airport Road in Mangaluru on Thursday after restoring one of the slabs that had sunken on June 15.

Connectivity to the international airport here will get restored on Friday afternoon as engineers from the Public Works Department (PWD) successfully conducted load test on the restored sunken slab of the Maravoor Bridge across the Phalguni.

Deputy Commissioner K.V. Rajendra in a communique here said that a formal notification allowing vehicular movement will be issued on Friday after he gets reports from the PWD. The load test was successfully conducted on Thursday, Dr. Rajendra said.

PWD Executive Engineer S. Yashvanth Kumar said that load test was conducted with trucks carrying loads up to 70 tonnes and the result was positive.

No disturbances were found in the structure during the test. All categories of vehicles will be allowed to pass through the bridge at 4 p.m. on Friday.

Once the new parallel bridge, which is now under construction, opens for traffic, the PWD will strengthen and rehabilitate all the remaining pillars of the old bridge so as to retain it for service, Mr. Kumar said.

Superintending Engineer, PWD, Mangaluru Circle, Ganesh S., AEE, PWD, K.T. Chandrashekaraiah and proprietor, Mugroady Construction, Mangaluru, Sudhakar D Shetty were present during the load test.

One of the slabs on the bridge towards the airport sunk by about 2.5 ft on June 15 forcing the authorities to immediately suspend vehicular movement. It was found that one of the supporting pillars sunk into its foundation resulting in the displacement of the slab. Vehicles were then diverted on alternative routes.

The Public Works Department, with expert advice from R.K. Jaigopal, who is Managing Director of Struct Geotech Research Laboratories Pvt. Ltd. in Bengaluru, executed the challenging work of restoring the sunken slab to its original position. The foundation was initially stabilised with boulders, sand dredging and sand blasting with nearly a 100 men working day and night to restore the slab. Thereafter, the slab was lifted using sophisticated jacks. Pedestal caps were installed and bearings were placed carefully on them to support the slab.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.