Metro’s S.N. Junction extension by May 2021

Land acquisition for the project to be over by month-end; tender process to select civil contractor in final stages

May 11, 2019 12:34 am | Updated 12:34 am IST - KOCHI

Jostle for space: The Petta-S.N. Junction corridor will be widened to four-lane by April 2020 as part of the Kochi metro’s 
S.N. Junction extension.

Jostle for space: The Petta-S.N. Junction corridor will be widened to four-lane by April 2020 as part of the Kochi metro’s S.N. Junction extension.

The Kochi metro’s long-pending 1.5-km extension from Pettah to S.N. Junction has received a boost, with Kochi Metro Rail Limited (KMRL) saying that the land acquisition process to widen the corridor and to build two stations en route will be completed by May 31.

A total of 2.75 acres have to be acquired for preparatory work (mainly to widen the road to four-lane), while two acres are needed for constructing stations at Vadakkekotta and S.N. Junction. The total extent of land needed is located in 182 land parcels, said a KMRL press release.

The tender process to select the civil contractor for the metro viaduct is in the final stages. Online tender will be opened on May 27. The contracting firm is expected to begin ground-level work (piling) on the stretch from June, said KMRL managing director A.P.M. Mohammed Hanish.

The agency will have to construct the metro viaduct from Petta to S.N. Junction, two elevated stations, and a two-lane bridge across Panamkutty river at Pettah. The existing bridge will be retained.

KMRL to execute

KMRL will directly execute the metro’s 1.5-km extension and later extend it further up to the Thripunithura railway station located a kilometre away from S.N. Junction (as part of the metro’s phase 1) and the upcoming phase 2 (the 11-km-long Kakkanad extension). “The district administration and KMRL officials are working in tandem to complete land acquisition, so that the preparatory work for the metro’s extension up to S.N. Junction can be completed in 10 months. All work, including the bridge, viaduct, and stations, can be completed by May 2021,” Mr. Hanish told The Hindu .

The metro agency has already appointed L&T Infrastructure Engineering Limited as the detailed design consultant for S.N. Junction and railway station extensions. The contract was awarded for ₹3.06 crore in June 2018, and the design is in the final stages. Following this, EQMS India Pvt. Ltd. was tasked with the preparation of the Environmental Mitigation/Monitoring Plan in April 2019.

The contract for widening the road along the proposed metro corridor to four-lane was awarded to Seguro Foundations & Structures Ltd. in December, and work has begun.

The State government had accorded administrative sanction of ₹123 crore for the preparatory work for the extension.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.