Metro steel bridge crosses Oliphenta railway bridge

1150 tonne edifice moved metre by metre

August 18, 2017 11:58 pm | Updated 11:58 pm IST - HYDERABAD

Engineering marvel: The 83-metre long link steel bridge in place over the rail lines on Oliphenta Railway Bridge.

Engineering marvel: The 83-metre long link steel bridge in place over the rail lines on Oliphenta Railway Bridge.

In the early hours of Friday when most citizens were still dreaming about the weekend ahead, L&T Metro Rail Hyderabad (L&TMRH) engineers, bleary-eyed having being awake the whole night shook hands with each other with big smiles.

Their eyes lit up with excitement and emotion as the mammoth metro rail steel bridge finally rested atop the two tall piers on either side of the Oliphenta Railway Bridge at about 18 metres or 60 feet from ground.

For about a week or so, the engineers have been carefully planning and pushing the 1150 tonne steel edifice from its erection site 200 metres away at the Chilkalaguda crossroads, metre by metre in the wee hours when most of the city slept.

‘Great feeling’

“It is like putting a satellite in the space, nothing could have explained the feeling among us. This is a lifetime opportunity,” smiles L&TMRH Chief Engineer (Construction) M.Y. Kondalu, flanked by his colleagues Prasanna Kumar, Pallam Raju, Imayavaramban and others.

Having obtained the traffic block period between midnight and dawn when the trains movement was halted and vents below closed for vehicular traffic for about a fortnight, it was a real challenging task for them to make use of the time frame and put the vital metro 83 metre-long link bridge in place.

Close to 20 engineers and more than 200 highly skilled workers have been at the site in fabricating the steel bridge and moving it almost round-the-clock.

Curve inside

While the metro viaduct will be taking a curve at the crossroads — Corridor Three: Nagole to Hi-Tec City/Raidurg — the steel bridge (9.5 metres high and 16.4 metres wide) will be positioned straight giving enough space for twin metro rail track to curve inside, inform senior engineers. Latest spherical bearings under the bridge will be holding it in place on the metro piers. Next step will be pouring concrete, laying the steel metro rails, cabling, signalling and electrification. Before that the front and back ‘trusses’ or noses used for pulling it will be dismantled. In about a month’s time, perhaps the metro trains could well be running on it for trial runs.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.