Minto bridge project misses the Games deadline

February 22, 2010 08:22 pm | Updated 08:22 pm IST - NEW DELHI

View of the Minto Bridge even as the road widening project has been stopped, in New Delhi on Monday. Photo: V. Sudershan

View of the Minto Bridge even as the road widening project has been stopped, in New Delhi on Monday. Photo: V. Sudershan

The plan to add two more tracks to the historic Minto Bridge in order to widen the heritage structure and enhance inter-State connectivity before the Commonwealth Games here will now miss its deadline.

The lack of coordination between the implementing agencies and practical difficulties in execution of the project given the existing traffic chaos around Connaught Place, have served as roadblocks in the timely completion of the project.

The decision to widen the bridge was taken in 2003 by Northern Railway to maintain uniformity as the road width below this bridge is narrow compared to the road width on either side.

According to Northern Railway, the project was to be implemented jointly by Northern Railway, Municipal Corporation of Delhi and New Delhi Municipal Council as one side of the area falls under the MCD and the other in New Delhi Municipal Council jurisdiction.

A Northern Railway official said: “As per normal procedure, the proportionate cost of widening of the bridge is required to be shared by the MCD, the Railways and the NDMC. A sum of Rs.400 lakh was released during 2003-04 on the basic demand of the Railway authorities for the project.”

However, the MCD claims that although most part of the project remains on paper, the civic agency has already completed most work under its jurisdiction.

An MCD official said: “The MCD was supposed to construct a retaining wall on one side to widen the road falling under its jurisdiction. While the retaining wall has been constructed, we are currently shifting a pump to avoid rainwater stagnation under the bridge. The road will be widened after the pump is shifted.”

However, Northern Railway and NDMC have not carried out any work under their jurisdiction so far. The reason, according to Northern Railway, is delay in getting requisite permissions.

“If the work was to be carried out all vehicular traffic in the area would have been restricted for six months. The Delhi Police Commissioner refused to grant us permission to divert traffic saying that because of the ongoing work related to Connaught Place redevelopment and construction of subways in the area there was already enough traffic chaos,” a Northern Railway official said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.