Hope College bridge to be ready soon

April 01, 2010 03:04 pm | Updated 03:04 pm IST - Coimbatore:

FOR COIMBATORE 31/03/2010: Mayor R. Venkatachalam (right), and Deputy Mayor N. Karthik  (left), inspecting at the Hope College Bridge in Coimbatore
Photo:S. Siva Saravanan

FOR COIMBATORE 31/03/2010: Mayor R. Venkatachalam (right), and Deputy Mayor N. Karthik (left), inspecting at the Hope College Bridge in Coimbatore Photo:S. Siva Saravanan

The ongoing road overbridge work across the railway line near Hope College on Avanashi Road and the widening and strengthening of Tiruchi Road stretch from Bypass Road junction till Stock Exchange is expected to be over by May end or June first week, Mayor R. Venkatachalam said.

The Mayor, who is also the Chairman of the City Development Committee constituted in connection with the ensuing World Classical Conference, recently inspected both the works.

With regard to the bridge work near Hope College, Mr.Venkatachalam said that the officials had been asked to speed up the works and make the entire stretch available for traffic for the conference.

The procession of floats and the mega rally for the conference would pass over the bridge and the same was pointed out to the railway authorities and contractors in-charge of the construction work.

Even the revision in the cost of construction as sought by the railways had been sent to the Government for approval and the Highways authorities already had an administrative sanction for laying an approach road to the three lane bridge coming up.

Near Hope College, a two-lane narrow old bridge was demolished and a three-lane bridge was constructed along with approach road and the same was being used for traffic flow now.

The other three-lane span works were in full swing and the works had already crossed 50 per cent mark and the remaining phase of work was being speeded up.

The railway authorities had also been invited to attend the next meeting of the City development committee to take stock of the situation and take measures to speed up the work. The bridge and the approach road works all estimated to be around Rs 4.88 crore would be completed by May end or positively by June first week.

Even the ongoing work for widening and strengthening the Tiruchi Road for seven km into a four-lane one from Bypass road junction to Stock Exchange had crossed more than 50 per cent mark, Mr.Venkatachalam pointed out.

The work taken up at a cost of over Rs. 15 crore included median and construction of three minor bridges near Rajalakshmi Mills, Singanallur Uzhavar Sandhai and Radharani Theatre.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.