IOC begins petrol production from Paradip refinery

The foundation stone for the refinery was laid by former Prime Minister Atal Bihari Vajpayee in May 2002.

January 17, 2016 02:18 pm | Updated September 23, 2016 12:59 am IST - Paradip (Odisha)

Indian Oil Corporation’s latest refinery in Paradip, Odisha, the first in over a decade for the nation’s largest fuel major, started production of petrol from the Rs. 34,555-crore facility on Sunday.

Prime Minister Narendra Modi will dedicate the 15 MMTPA Paradip Refinery, which will primarily be producing BS-IV fuels and serving the eastern and south-eastern markets apart from exports, to the nation on February 7.

The commissioning of the refinery comes after 14 years, owing to many flip-flops by the Naveen Patanik government on incentives, withdrawal of its foreign partner Kuwait Petroleum and stiff frequent opposition from locals, state politicians and NGOs apart from two killer cyclones.

The foundation stone for the refinery was laid by former Prime Minister Atal Bihari Vajpayee in May 2002, which again was a full one decade after the project was proposed by the PV Narasimha Rao government in July 1992.

“We have completed one of the most critical steps of the refinery today. With our 3.9 MMTPA motor spirits unit going critical, we have only VGO-HDT (vacuum gas oil hydrotreater) to be commissioned that will be done by mid next month.

“This refinery complex is the most modern facility in the country and also our first and the largest greenfield facility on the East Coast,” Ramjee Ram, executive director in-charge of the Paradip Refinery project, told reporters during a plant visit ahead of the formal commissioning.

This 15-million tonne refinery is also the largest on the country’s Eastern coast, and is equipped with the latest technology, including IOC’s own patented IndMax technology for better and higher LPG output.

The Rs. 34,555-crore project, which had incurred a cost overrun of over Rs. 3,500 crore due to delays that it had to face apart from two cyclones, is coming up at a 3,350 acre area adjoining the Paradip Port.

The project includes a sprawling, modern residential complex that boasts of a Delhi Public School, a modern stadium complex, among others. The refinery complex spans over 2,100 acres, while the proposed Rs. 35,000-crore petchem will come up on the north bank of the jetty.

It also has a 17 metre deep natural draft for its oil jetty that can berth very large ships and has captive multi fuel power plant that can generate over 360 MW electricity.

Though the refinery will primarily be processing high-sulphur crude oil, cheaper by $ 2-3 a barrel, Ram said the facility can process any type of crude from the Gulf nations, Africa and South America.

However, he was quick to add that a final call on the feed will be taken by the central procurement cell, which decides mix of the crude to be sent to different refineries.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.