360 infra projects show cost overruns of ₹3.88 lakh crore

Of the 1,608 projects monitored by the Ministry of Statistics and Programme Implementation, 360 reported cost overruns and 550 time escalation

October 20, 2019 11:13 am | Updated 11:13 am IST - New Delhi

Photo for representation.

Photo for representation.

As many as 360 infrastructure projects, each worth ₹150 crore or more, have shown cost overruns to the tune of over ₹3.88 lakh crore owing to delays and other reasons, a report said.

The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth ₹150 crore and above. Of these 1,608 projects, 360 reported cost overruns and 550 time escalation.

“Total original cost of implementation of the 1608 projects was ₹19,17,796.07 crore and their anticipated completion cost is likely to be ₹23,05,860.33 crore, which reflects overall cost overruns of ₹3,88,064.26 crore (20.23% of original cost),” the Ministry’s latest report for June 2019 said.

According to the report, expenditure incurred on these projects till June 2019 stood at ₹9,35,021.39 crore, which is 40.55% of the anticipated cost of the projects.

However, it said the number of delayed projects decreases to 474 if delay is calculated on the basis of latest schedule of completion.

Further, it said that for 644 projects neither the year of commissioning nor the tentative gestation period has been reported.

Out of 550 delayed projects, 182 projects have overall delay in the range of 1 to 12 months, 119 projects 13 to 24 months, 133 projects reflect delay in the range of 25 to 60 months and 116 projects show delay of 61 months and above.

The average time overrun in these 550 delayed projects is 39.24 months.

The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment.

The report cited other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist issues, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others.

It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.