Union Carbide’s preoccupation with maintaining a majority stake in its Indian subsidiary led to cost-cutting on waste disposal systems
On June 26, U.S. Federal Court Judge John Keenan declared that the U.S.-based Union Carbide Corporation (UCC) and Warren Anderson were not liable for damages caused by the toxic wastes dumped in Bhopal. Neither could the two be asked to clean up, he ruled. That responsibility, Keenan said, lay solely with UCC’s Indian subsidiary, Union Carbide India Ltd (UCIL).
Keenan argues that UCIL consulted with “UCC about its waste disposal plans and on non-environmental business matter like its strategic plan. However, nothing in the evidence suggests the necessity of UCC’s approval for the actions about which plaintiffs complain.”
What documents say
Official UCC documents unearthed by Bhopalis through a process under U.S. law known as “discovery” suggest otherwise. The one thing that drove the design process towards disaster was UCC’s preoccupation with maintaining a majority stake in UCIL. In 1973, with the Foreign Exchange Regulation Act (FERA) set to change, UCC was worried about losing its majority stake in UCIL. The MIC-Sevin pesticide project was conceived because such core sector projects were eligible for exemption under forex rules that limited foreign stakes in Indian companies to 40 per cent. However, the Indian government also required that 25 per cent of project budget be raised through Indian equity.
At the then estimated $28 million, UCIL’s pesticide project would have diluted UCC’s stake to below 50 per cent. A 1973 UCC memo is clear: “Our specific objective is not to accept any conditions which would reduce our equity below 51 per cent.” To do this, UCC decided to underinvest. The $28 million project was to be executed at $20 million, 25 per cent less than originally budgeted.
The first underinvestment is detailed in a 1973 Capital Budget Plan of the UCC management committee. That committee, which included Anderson, knew that “The comparative risk of poor performance … is considerably higher in the UCIL operation than it would be had proven technology been used throughout.” But the committee went ahead and ratified a decision to use unproven technology arguing that “UCIL finds this business risk … acceptable, however, in view of the desired long term objectives of minimum capital and foreign exchange expenditures.” The note specifically acknowledges that the carbon monoxide and I-napthol processes have not been tried commercially elsewhere, and that “the waste streams arising out of this combination of materials is new and, accordingly, affords further chance for difficulty.”
Waste handling
On three occasions — in 1973, 1977 and 1981 — UCC considered shutting down the Indian subsidiary’s agricultural products operations. On all three occasions, it decided against the proposal.
Instead, it opted for austerity keeping in mind the need to retain a controlling stake in UCIL. That was possible only by keeping the pesticide project going.
Compromises on the waste handling system were an integral part of the belt tightening exercise. UCC’s plant in Institute, West Virginia, had a more evolved waste management system. It discharged treated waters to the Kanawha river. The underfunded Bhopal plant was expected to construct huge open air tanks to evaporate untreated wastewater containing cyanide, arsenic, cadmium, lead, phenols and carbaryl pesticides. A UCC memo from July 1972, when the project was being conceptualised, records that the solar evaporation ponds posed the risk of contaminating groundwater and releasing toxic naphthol emissions to air.
The design for the evaporation ponds was fatally constrained by the need to cut corners — a need geared solely towards ensuring UCC’s majority stake in UCIL. A January 1977 memo documents a meeting between UCIL and its contractor for constructing the evaporation ponds. The document states that the following was discussed and agreed: “UCIL emphasised the need for reduction for cost of the Pond as much as possible and it was informed by them that certain seepage/effluent from the pond can be accepted by them provided there is corresponding reduction in the cost.”
UCIL told UCC it was opting for a plastic liner in the place of the more expensive and less permeable clay liner mentioned in UCC’s guidelines criteria. UCC did nothing to stop it. By 1982, within three years of operation, telex messages sent to UCC recorded that the ponds were already leaking. Again, UCC did nothing. Between 1984 and 1994, when it retained a controlling stake on UCIL, it refused to clean up the environment.
The Keenan judgment
Keenan states in his 56-page judgment that UCC was merely a shareholder, and had no “duty of care” in preventing its subsidiary from causing harm. Far from being a mere shareholder, UCC had actually sanctioned the $20 million for the pesticide project despite glaring design deficiencies.
Keenan’s history of rejecting Bhopalis’ claims and parroting UCC’s lines is as old as the disaster itself. In 1986, Keenan dismissed compensation suits against Carbide filed by Bhopal victims, thereby denying them the substantial jury awards that would have resulted from a U.S. trial. Endorsing Carbide’s arguments, he ordered that India had a well-developed judicial system, and that UCC could be expected to abide by the ruling of Indian courts. Belying Keenan's faith in UCC and Anderson’s respect for Indian law, both parties are still absconding from Indian courts.
Indeed, it is the Bhopalis’ misfortune that all their cases in the U.S. have come up before Judge Keenan. Even this case was dismissed by Keenan three times. Each time, it was reinstated by the Appeals court. This time too, Bhopalis will appeal.
(Nityanand Jayaraman is a writer, and volunteer with the campaign for justice in Bhopal.)
Keywords: Union Carbide, Warren Anderson, Bhopal gas tragedy





Thanks for good clarifications from Sri. Nityanad Jayaraman.
Regarding culpability, it has been reported elsewhere that many engineers working
at UCIL were aware of the considerable risk of an MIC discharge given the extreme
cost-cutting and lax safety measures implemented in Bhopal, with several
engineers having left UCIL and taken up jobs which would keep them away from
Bhopal.
Obviously, these people knew what was going to happen but UCIL management
and UCC-US (which was the actual management) kept ignoring their pleas for
better safety measures which would have cost money. It is hard to imagine a
clearer evidence of culpability on part of UCC.
Dear Mr. Mukundagiri Sadagopan:
Just a clarification on your comment. The case in the US Federal court related to damages arising out of contamination caused by the routine dumping of toxic wastes during the five years that the plant operated -- from 1979 to 1984. The contamination actually has nothing to do with and predates the disaster. Even if the disaster had not happened, the contamination would have taken its toll. The fact that Union Carbide USA was a 51 percent shareholder at the time that the contamination occurred, and for a decade after the disaster occurred ought to be sufficient for anyone with common sense to conclude that it was at least partly, if not majorly, liable for the damages. Indeed, in the infamous settlement of 1989 endorsed by the Indian judiciary, UCC-US was asked to pay $425 million out of the total settlement amount of $470 million. The Indian subsidiary was required to pay the remainder.
'Justice Compromised' is the apt title on the decision by the US Justice on the Union Carbide liability to the Bhopal tragedy. The decision would have been different if the same incident happened in some other developed or influential countries. So far, Indian government were not able to influence the US government for the need to pay the compensation which will take generations to clean up and to bring normal life.
In the recent 2G Supreme court decision, many countries were trying to influence Indian government to protect the investments of the copanies from their country where there is no human life loss. Atleast this should open up the eyes of the Indian government and influence the US government for a favourable decision to the victims of Bhopal tragedy.
Indian government, let us be more prudent in protecting the lives of the Indian people and also the natural resources. Let us not open the entire country to MNC's in the name of development where the locals are not protected
It is rather pathetic to continue to bemoan the helplessness of the
Indian government to get justice on the Bhopal disaster in the
American courts presided over by prejudiced and vindictive, the likes
of Justice Keenan. Any more appeals are not likely to deliver any
impartial justice. With the malefic intentions to retain major
shareholding prevailing over safety and human rights norms, the parent
UCC had deliberately schemed a 25% lower investment adopting a risk
prone unproven technology, the one rejected by their own Virginia
Plant. The efforts should now concentrate to move the appeal to the
Court of International justice. For a global, Bhopal like disaster,
the overwhelming evidence of deliberate and disdainful compromise to
human safety should prevail over the loopholes in the nuances of
semantics in the bilateral agreements, particularly in the context of
such a deceit committed on innocent citizens of a client nation, that
trusted the host nation for its expertise
It is obvious that the Bhopal Gas victims will not get a fair trial in the US. Even the Indian judiciary failed to protect the interests of the victims. It has been 28 years since the tragedy occurred in which thousands of people were killed and many thousands permanently impaired.Reports indicate that many victims are yet to receive compensation. The Corporates and individuals responsible for the tragedy have got have Scot free.
In the Mexico oil spill in 2010 British Petroleum had to pay US$ 20b to the people affected by the oil spill, even though there was no loss of life. It had to further spend $18b for cleaning the Mexican Gulf.
Dow Chemicals which is the parent company of Union Carbide is so influential that it can subvert justice. It is one of the sponsors of the London Olympics.
Rogue Corporations all over the world are polluting the environment, destroying marine life. spreading diseases and affecting the lives of millions of people with impunity.
Can you expect any justice to the victims when some of India's top lawyers serve the MNCs?
It is indeed regrettable that victims of the 1984 tragedy of Union Carbide India at Bhopal are still without full compensation for their irreparable losses. The evidence shows that the measures to control or stop seepage and effluent treatment were inadequate. The solar evaporation ponds for dangerous chemicals were indeed unsafe. While these practices were condemnable, it is not clear that the specific accident that caused the death of thousands was directly caused by these defects. The mass deaths were caused hours before dawn on December 3, 1984, when workers were on a tea break, by large quantities of water being piped into a Methyl-Iso-Cyanate storage tank. How exactly did water get into the MIC tank and who is responsible for the steps leading to this fateful error? Answers to these are critical to determine culpability in this case. It is not clear if the plaintiffs laid out a step by step path leading from the accident to the doors of (now defunct) Union Carbide, USA.
Please Email the Editor