The Environment Ministry has handed the Lavasa Lake City a lifeline, even as it declared the project unauthorised.
If the Lavasa Corporation is prepared to pay a fine, set up an Environmental Restoration Fund and follow strict terms and conditions, the Ministry is prepared to consider the future of the housing project on merits, the final order issued by the Ministry on Tuesday said. In the meanwhile, the stop work order remains in place, so that status quo is maintained at the construction site.
The Ministry has been investigating the Rs. 3,000 crore project’s compliance with environmental norms since it issued a show cause notice and stop work order in November 2010, based on complaints by civil society activists.
The Ministry found that the project, involving the development of hill station townships near Pune, is in violation of the Environmental Impact Assessment notification of 1994, its 2004 amendment and the fresh EIA notification of 2006. A site visit by a Ministry team earlier this month also found that the project has caused considerable environmental damage.
Despite these violations, the Ministry could allow the project to continue, thanks to the investments and labour which have already gone into the project, third party rights which are accrued, the employment generated, and the “claimed upliftment of the area”.
Apart from the “substantial penalty” for violation of green laws, Lavasa has been told to create an Environmental Restoration Fund, with “sufficiently large corpus” to be managed by an independent body of stakeholders under Ministry supervision. The Ministry is also imposing “stringent” conditions to ensure that no further environmental degradation takes place, while a time bound schedule is set up to rectify the damage that has already been done.
Lavasa has been told to submit detailed reports of past and future work plans and audited financial statements. It will also have to submit a comprehensive EIA report and management plan.
If the company gives “relevant and credible material”, the Ministry is prepared to consider the project on merits, said the order.
Keywords: Lavasa project, environmental clearance








warm welcome our environment minister/ dept your view no doubt great,
but lavasa follow 100% environment policy, if any dispute u sagest him,
but its not suitable decisions to stop work, due to at present u know
the our all kind of situation in our planet, please apply any suitable
norms
Law should be equal to everybody , whether it is Lavasa or any XYZ. 99% Industries in India are least bothered about environment. Lavasa should be punished heavily. Other ministers including PM should learn from this. Especially Agriculture Minister Mr. Sharad Pawar. I don't Know what he is doing. Thanks to Minister Shri Jairam Ramesh and we salute to way he is going.
The punishment and penalty should be very severe that nobody repeats this kind of mistake. Moreover this should send out a signal to banks and investors who believe that they can start the project make huge investments and bend the 'Law of the Land' citing reasons like growth, employing thousands of people. The people of India should request the minister to take stern action against(as per law) Lavasa. All of us have the responsibility to leave a better planet for the future generation.
Jairam Ramesh in action. Good to see that. The order of demolition of Adarsh building and orders to Lavasa will definitely act as deterrent. Cheers to our Green Minister who is making some sense in nonsense government of Manmohan Singh
No!! That should not happen at all.Yes the company had invested a lot in the project that does not mean govt should let them go with a fine. It is not traveling without ticket in railways. It should be made to make good for the damage and with exorbitant fine so that others do not repeat it. Then the purpose of law is upheld.
On the first hand why was this project given a green signal. Those who did it they should also be accounted and punished for it.
Please Email the Editor