Sethusamudram project: SC grants two weeks’ time to T.N.

April 01, 2013 05:12 pm | Updated November 17, 2021 04:16 am IST - New Delhi

Dredging work near the Adam's Bridge in Rameswaram as part of the Sethusamudram Ship Channel project. File photo: K. Ganesan

Dredging work near the Adam's Bridge in Rameswaram as part of the Sethusamudram Ship Channel project. File photo: K. Ganesan

The Supreme Court on Monday granted two weeks’ time to Tamil Nadu government to apprise it of its stand on the controversial Sethusamundram project after the Centre had said it intended to pursue its implementation.

“File your (Tamil Nadu) response affidavit within two weeks and give copies (of affidavit) to the Solicitor General and others at least two-three days before the filing. The pleadings in the case is almost complete,” a bench of justices H.L. Dattu and J.S. Khehar said.

During the hearing, Janata Party President Subramanian Swamy, one of the petitioners, said now the court should decide the issue as the Centre had rejected the R.K. Pachauri Committee report that had found the entire Sethusamudram project unviable on two fronts -- economically as ecologically.

The Centre, in its affidavit, had said it intended to go ahead with the Rs 25,000 crore Sethusamudram shipping channel project on the ground that it has economic, navigational and strategic advantages and moreover an expenditure of Rs 829.32 crore has already been incurred on it as on June 30, 2012.

The court had earlier asked the Centre to apprise it of its stand on the controversial project following the Pachauri Committee report.

The case relating to Ram Sethu had come under judicial scrutiny as a batch of petitions were filed in the apex court against the ambitious project, whose execution, the petitioners feared, could damage the mythological bridge.

Sethusamudram project is aimed at constructing a shorter navigational route around India’s southern tip by breaching the Ram Sethu, said to have been built by Lord Rama’s army of monkeys and bears to Ravana’s kingdom Lanka.

As per the Sethusamudram project, the shipping channel is proposed to be 30 mt wide, 12 mt deep and 167 km long.

The Prime Minister had appointed the RK Pachauri Committee after the apex court had asked the government to explore an alternative alignment for the shipping channel to prevent any damage to the mythological bridge.

The committee, in its report, had raised questions on the alternative alignment after taking into account various aspects including its economic and ecological assessment.

It had said the entire Sethusamudram project was unviable economically as well as ecologically.

The court, on August 31, 2007, had restrained the Centre from damaging Ram Sethu while dredging for the Rs. 25,000 crore project inaugurated in 2005.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.