Nod for loading of real fuel in Kudankulam

May 13, 2012 12:08 am | Updated November 16, 2021 10:45 pm IST - NEW DELHI:

The Atomic Energy Regulatory Board (AERB) has given its approval for the removal of dummy fuel and loading of real fuel (enriched uranium) in the first unit (1000 MW capacity) of the Kudankulam Nuclear Power Plant (KNPP) in Tamil Nadu.

The loading of real fuel would begin soon and thereafter, a trial run would go on for approximately 20 days before attaining criticality (commissioning), Minister of State in the Prime Minister's Office (PMO), V. Narayanasamy said here on Saturday.

Talking to The Hindu , the Minister said a team of 13 scientists had carried out a detailed study of the plant, including the pressure vessel and its internal components, before giving the ‘go ahead' on Thursday.

The activity in the second unit (also 1000 MW) was nearing completion and more than 95 per cent of the work there was over, he said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.