PWD works on the slow lane

Poll code violation: all tendersfloated after March 4 cancelled

April 04, 2014 11:39 am | Updated May 23, 2016 06:33 pm IST - THIRUVANANTHAPURAM:

The three-month period from March, crucial in the execution of Public Works Department (PWD) projects in the State, has been of minimal use due to the model code of conduct taking effect ahead of the Lok Sabha polls.

The PWD was forced to cancel all tenders floated after March 4 as the poll dates were declared by the Election Commission of India (ECI). A directive was issued after the government came to know that tenders were being floated by the PWD even though the code of conduct was in force.

PWD barred

The PWD had also been barred from awarding contracts floated, official sources told The Hindu .

With this, the PWD would not be able to kick off new works relating to road, bridges, and buildings till May. The March-May period was ideal for taking up major works in view of the climate and closure of educational institutions for summer vacation, sources said.

The PWD had been asked to invite fresh tenders and bids only after April 10, the polling day, after seeking the concurrence of the government.

The directive would delay work on the Rs.5,581-crore monorail; the elevated MRTS in Thiruvananthapuram and Kozhikode; the retendering of the remaining work on the NH 66 bypasses in Kollam and Alappuzha; and the Rs.5,100 crore State Road Improvement Project of 1200 km of major State and district roads initiated by the Road Infrastructure Company Kerala.

Ongoing work hit

The work on the Chengannur-Ettumanur stretch of MC Road, under the World Bank-aided Kerala State Transport Project II had also been hit. The retendering of the work in the stretch was on the basis of a recent directive of the World Bank to the State.

Confirming that all new works had come to a standstill, a top official said it was a blessing in disguise for the Finance Department which was facing a financial crisis.

Though tenders could be floated after April 10, the works could be awarded only after the poll process was completed, sources said. “The PWD will be able to complete the formalities of tender and award new works only by May end,” he added.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.