MRPL to reduce dependence on fresh water

Board of Directors gives in-principle approval to commission desalination plant by 2020

October 01, 2017 11:19 pm | Updated 11:19 pm IST - MANGALURU

Karnataka , Mangaluru : 23/09/2016 : The third phase plant of Mangalore Refineries and Petrochemicals Ltd, (MRPL), off Mangaluru. Photo : Anil Kumar Sastry

Karnataka , Mangaluru : 23/09/2016 : The third phase plant of Mangalore Refineries and Petrochemicals Ltd, (MRPL), off Mangaluru. Photo : Anil Kumar Sastry

The Mangalore Refinery and Petrochemicals Ltd. (MRPL) has big plans to reduce its dependence on fresh water sourced from Netravati at a time when demand for human consumption is on the rise and resources are scarce.

Its Board of Directors recently gave in-principle approval to set up a seawater desalination plant that can substantially reduce MRPL’s fresh water consumption.

The plant, proposed on about 14 acres of land to be taken on lease from New Mangalore Port Trust (NMPT), is likely to have 5 million gallon per day (MGD) capacity to produce fresh water initially, which can be scaled up depending upon the requirement.

MRPL Managing Director H. Kumar told The Hindu that the board, while giving in-principle approval, wanted to deliberate on some finer issues, including the cost. This would be discussed shortly and a final decision will be taken, he said.

Director (Refinery) M. Venkatesh said MRPL’s endeavour is not to take fresh water even when the refinery expands under the Phase IV.

Water sources

At present, MRPL draws about 8 MGD of Netravati waters, 3 MGD of treated sewage from Mangaluru and uses another 2 MGD of in-house recycled water. The effort is not to increase fresh water intake even as MRPL has been asking Mangaluru City Corporation to scale-up treated domestic sewage supply, Mr. Venkatesh said.

Mangaluru residents use about 27 MGD of Netravati waters, while the city has installed capacity to treat about 18 MGD of sewage.

However, not all sewage generated in the city goes to treatment plants and much flows directly into the Netravati and Phalguni (Gurupura) rivers.

Mr. Venkatesh said desalination by MRPL would not result in brine — a situation where seawater becomes saltier. Both suction and discharge of seawater takes place at least by about 800 m from the seashore and the discharges will easily be dissolved into the sea, he said.

While MRPL is working on the finer aspects of project cost, Mr. Venkatesh said advancement in technology has brought down the cost of production considerably, from about ₹70 per thousand litres a decade ago to about ₹40 per thousand litres.

MRPL has set a target of April-May 2020 for commissioning the desalination plant after following the requirements, Mr. Venkatesh added.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.