Cancellation of coal blocks after IMG report: Jaiswal

September 02, 2012 11:24 am | Updated August 03, 2016 04:52 am IST - Kanpur/New Delhi

New Delhi: Union Coal Minister Sriprakash Jaiswal speaks during a press conference highlighting the activities and achievements of Ministry of Coal 2009-10 & 2010-11 in New Delhi on Tuesday. PTI Photo by Vijay Kumar Joshi(PTI5_31_2011_000050B)

New Delhi: Union Coal Minister Sriprakash Jaiswal speaks during a press conference highlighting the activities and achievements of Ministry of Coal 2009-10 & 2010-11 in New Delhi on Tuesday. PTI Photo by Vijay Kumar Joshi(PTI5_31_2011_000050B)

Against the backdrop of opposition pressure, the fate of 58 coal blocks will be reviewed on Monday at a meeting of an Inter-Ministerial Group (IMG), on whose recommendations wrongful allotments and cases in which mining has not started can be cancelled.

Coal Minister Sriprakash Jaiswal said an IMG has been set up to examine the pros and cons and based on its report any number of allocations can be cancelled.

He said the IMG will give its report by September 15.

"Right now, no allocations are being cancelled. On the basis of the IMG report, the allocations which were made in a wrongful manner or those allottees who have failed to start production of coal in a time-bound manner may face action. Any number of coal blocks can be cancelled," Mr. Jaiswal told reporters in Kanpur.

The government has already issued de-allocation notices to 33 government firms and 25 private entities in this regard. But the opposition has demanded cancellation of all 142 allocations mentioned in the CAG report.

In its report tabled recently in Parliament, the CAG stated that undue benefits to the tune of Rs 1.86 lakh crore were extended to private firms on account of allocation of 57 mines to them.

The IMG comprising representatives from different Ministries may recommend cancellation of such blocks, which did not comply to the development norms.

Sources said the firms in their replies furnished to the Ministry have cited various reasons, including land acquisition problems, delays in forestry and environment clearances and law and order problems for delays in developing the blocks.

The government in April began the process of issuing notices to companies that failed to develop the 58 coal blocks within the stipulated time.

The notices were issued to firms like Reliance Power's Sasan, Tata Power, Hindalco and Grasim Industries, ArcelorMittal, GVK Power, MMTC and others.

In June, the government formed an IMG to review progress of coal blocks allocated to companies for captive use.

Of the total 195 coal blocks allocated to both public and private firms over a decade, only 30 mines have begun production as per the government records.

The government, last year had cancelled the allocation of 14 coal mines and one lignite mine to companies, including NTPC and DVC for failure to develop the blocks.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.