Beas tragedy: role of private power projects under the scanner

Questions also being raised on role of SLDC

June 13, 2014 01:09 am | Updated November 17, 2021 04:27 am IST - PANDOH/ MANDI

Following the tragedy on the Beas, questions are being raised on the role of private power producers in Himachal Pradesh and the State Load Dispatch Centre (SLDC).

The SLDC, an autonomous body, is tasked with monitoring power generation and it is on its recommendation that production is adjusted in all State-run projects, according to the Power Ministry.

An important question being raised is why are public sector power projects the only told to generate less power to save the Northern Grid from a surplus production. Also, at a time when the plains, including the National Capital Region, need more power, projects in Himachal Pradesh are being told to create less power even as the glacier-fed rivers are overflowing.

Another question that is being asked is whether the Mandi Divisional Commissioner, who is enquiring into the incident, will examine the role of SLDC in adjusting the generation schedule of public sector units and not of private projects.

Around 300 cusecs of water was released on Sunday by the Larji project to stop production on Sunday and divert its water to the main river instead of going from headrace tunnel to the power house.

According to sources in the State power ministry, the SLDC ordered closure of two of the three units (of 42 MW each) of the 126 MW Larji Project which resulted in the opening of the main gates of the dam since much less water is required to run the only remaining unit inside the project. A similar order was passed by the SLDC to public sector Bhaba, Giri and Parvati projects to reduce production as per requirements of the Northern Grid.

Independent power producers, sources said, were left free to produce any amount of power and reduced production by government-run projects helps them sell more power at higher rates. Private projects such as Jaypee’s 1000 MW Karcham Wangtoo produced around 1200 MW of power even during the scale down ordered by SLDC and Regional Load Dispatch Centre, according to sources.

The SLDC, which takes instructions from the Northern Grid RLDC and the National Load Dispatch Centre (NLDC), has claimed that the orders were issued on the latter’s instruction.

The NLDC had claimed there was no demand for power and hence generation needed to be stopped to save the grid from a possible collapse. This resulted in the Larji project cutting generation to one-third and releasing the surplus water into the Beas on Sunday evening when students from Hyderabad were on a break and taking photographs inside the river bed.

The State Committee of the CPI(M) has pointed towards a nexus between the SLDC and private power producers in the State.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.