Japan suspends 35 tsunami reconstruction projects

November 28, 2012 04:05 pm | Updated November 17, 2021 05:53 am IST - TOKYO

File photo shows Minamisanriku town submerged in water, after a strong earthquake triggered tsunami in Miyagi prefecture, Japan on March 12, 2011.

File photo shows Minamisanriku town submerged in water, after a strong earthquake triggered tsunami in Miyagi prefecture, Japan on March 12, 2011.

Japan’s government has suspended 35 projects included in a budget for reconstruction from the March 2011 earthquake and tsunami after criticism the spending was not directly related to recovery from the disasters.

As much as a fourth of the ¥11.7 trillion ($148 billion) budget had been earmarked for unrelated projects, including subsidies for a contact lens factory in another region and research whaling.

No specific reason was given for each project, though Noda and other officials have vowed to cut spending not directly for reconstruction. Many of the projects in the budget were included on the pretext they might aid Japan’s economic revival.

“Some of the projects are being deferred to 2013,” Chief Cabinet Secretary Osamu Fujimura told reporters in a regular briefing. “But Prime Minister Noda said the spending really must be committed to reconstruction.”

Among the projects put on hold was a plan to boost the Japan “brand” through lecture tours, money earmarked to pay for Cabinet-sponsored discussions on “social inclusiveness,” and quake-resistance renovations for various government ministries.

Minutes from a committee meeting held last month showed Cabinet ministers concluding that while projects unrelated to the disaster were legal, it would be better to focus spending on the disaster zone.

The committee adopted new guidelines this week requiring that reconstruction funds be disbursed through a special government account devoted to programs in the disaster area, which includes much of Japan’s northeastern coast.

A notice on the website of the Reconstruction Ministry said the Finance Ministry and other government agencies would work to “strictly rectify” the budget, and may suspend other projects.

The government decided to boost spending on reconstruction from the ¥19 trillion ($237.5 billion) meant to be spent by the end of March 2015.

Progress on reconstruction has been hindered by a lack of local government staff and other experts, disagreements over how and whether to rebuild some towns obliterated by the tsunami, and the sheer scale of the destruction.

A report issued on Tuesday showed only 47 per cent of planned projects had begun work. About 60 per cent of the 9.6 million tons of tsunami debris has been cleared, but only 11 per cent of it processed. Reconstruction of fisheries and fishing ports and rehabilitation of farmland has also lagged.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.