Failed sea trials likely to delay delivery of INS Vikramaditya

September 17, 2012 01:20 pm | Updated 07:23 pm IST - MOSCOW

INS Vikramaditya has failed sea trials and its delivery to the Indian Navy may be again delayed by almost a year, Russian media reported citing defence and industry sources.

Seven out of the aircraft carrier’s eight steam boilers broke down when they were run at maximum power to enable the ship develop its top rated speed of 30 knots, an unnamed official of the state arms exporter Rosoboronexport told the Kommersant daily.

The official explained that the firebrick insulation of the boilers crumbled under impact of high temperatures.

Sources in the shipbuilding industry told the Kommersant that the boilers will have to be removed for inspection or replacement through cuts to be made in the Vikramaditya’s hull. Replacing the boilers will cost Russian shipbuilders more than one billion roubles (over $30 million), the sources said.

The propulsion system failure will push back the ship’s delivery from December this year to October next year “at the earliest,” according to Russian sources, as repairs can only start next spring because of harsh winter conditions in the Arctic seaport of Severodvinsk, where the ship has been retrofitted.

However, a designer of the boilers rubbished the report. He said the repairs would take three-four months because was no need either to replace the boilers or to take them out.

“All that needs to be done is to replace the firebricks without dismantling the boilers,” Vasily Kukin, deputy head of a specialised boiler design bureau, told the Interfax wire.

The designer explained that the Indian side had objected to the use of asbestos in the insulation of the boilers because of feared health hazards and the manufacturer used other material which turned out to be sub-quality.

The mishap comes as is a major embarrassment for President Vladimir Putin as he prepares to pay an official visit to India next month.

Under the 2004 original contract for the remodelling of the heavy aviation cruiser Admiral Gorshkov into a light aircraft carrier the Vikramaditya was to be handed over to the Indian Navy in 2008, but the delivery has been delayed as the vessel’s conditions turned out to be much worse than expected and the cost of refurbishment escalated from just over $600 million to more than $2 billion.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.