Finally, Panniyankara rail overbridge turns reality

December 19, 2016 12:12 am | Updated 08:03 am IST - KOZHIKODE:

DMRC Principal Advisor E. Sreedharan explains the alignment of Panniyankara overbridge and proposed monorail to Chief Minister Pinarayi Vijayan during the inauguration of the overbridge in Kozhikode on Sunday.

DMRC Principal Advisor E. Sreedharan explains the alignment of Panniyankara overbridge and proposed monorail to Chief Minister Pinarayi Vijayan during the inauguration of the overbridge in Kozhikode on Sunday.

With the inauguration of the Panniyankara rail overbridge (ROB) by Chief Minister Pinarayi Vijayan on Sunday, a long pending dream of the city finally became a reality.

Local residents joined Ministers, political leaders and councillors to celebrate the official inauguration of the bridge. Clubs made merry by distributing payasam and band troupes performed on the bridge.

All these years, the people of Payyanakkal and Chakkumkkadavu have had a harrowing time, travelling 3.5 km to reach the city. The narrow Kallai Road would become congested when the railway gate at Payyanakkal closed. “Now a big traffic problem on the arterial road has been solved,” the Chief Minister said.

The Delhi Metro Rail Corporation (DMRC) tasked with the work was able to construct the bridge at a cost of Rs.40 crore though the original estimate was pegged at Rs.50.16 crore.

Presiding over the inaugural function, Minister for Public Works G. Sudhakaran said the State government had planned to execute road projects worth Rs.1,000 crore for Kozhikode city under the Kerala Road Fund Board.

Project over the years

Tracing the history of the project, DMRC Principal Advisor E. Sreedharan said the State government had given administrative sanction of Rs.6.25 crore for the Panniyankara road overbridge on May 22, 1997. It was then conceived as a 400-metre L-shaped bridge over the rail line connecting Payyanakkal to Kozhikode. However, the project was delayed due to land acquisition. The State government on August 18, 2005, gave administrative sanction of Rs.60 lakh to acquire land. Subsequently, a sum of Rs.40 crore was allotted for the project.

At the time, the government had proposed a mono rail project from Medical College to Meenchanda. So the alignment had to be altered to suit the mono rail project. Thus, the DMRC, which had been tasked with project in August 2012, submitted a proposal with a T-shape overbridge with provision for proceeding from Payyanakkal to Kozhikode and Meenchanda sides, Mr. Sreedharan said.

The construction activities began in April 2014 and the time allotted was 18 months. But, the completion was delayed by a year. Of the 141 cents required for the project, the land acquired was 98 cents.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.