Underneath Chennai

It’s a project most of the city is looking forward to. How is Metro Rail, expected to lessen some of our traffic and transport woes, getting along? Sunitha Sekar takes a look at its underground station work

February 15, 2013 04:03 am | Updated June 11, 2016 02:57 pm IST - Chennai

For most residents, the construction of underground stations for the city’s dream transport project — Metro Rail — is mostly a lot of noise, traffic diversions, and the occasional sight of massive machines.

But behind the heavy iron barricades that dot many of Chennai’s arterial roads, tunnel boring machines (TBMs) have been relentlessly drilling through rocky surfaces to make way 19 underground stations that will be part of a complex 24-km underground rail network. And these gigantic devices are being handled by workers not just from India, but also China, South Africa, Russia, Germany and Nepal.

In June last year, Chinese workers arrived in the city and the first TBM began operating in Nehru Park in July. Eight months on, work has progressed considerably, well on its way to meeting the 2015 deadline.

Chennai Metro Rail Limited (CMRL) plans to operate a total of 11 TBMs to tunnel through various areas at its sites, including Nehru Park, Washermenpet, May Day Park, Shenoy Nagar and Saidapet. Of the 11, seven TBMs are fully operational at Nehru Park, Washermenpet, May Day Park and Shenoy Nagar and are at different stages of excavation.

“The progress of the underground work is heavily driven by the geological conditions prevailing in the area. But we are trying our best to foresee changes and meet deadlines,” said V. Somasundaram, chief general manager (construction) of CMRL.

“We are making plans in advance to face geological challenges and intend to complete all of the work by 2015. We propose to finish at least 20-30 percent of the station work by the end of 2013,” he added.

At present, the May Day Park, Government Estate, Shenoy Nagar and Saidapet stations have had the diaphragm wall panel (a box-like concrete structure) for the station placed and completed. While the casting of roof slabs (where the entry-exit of the station will be) has taken place at Washermenpet, Saidapet, Kilpauk, Pachaiyappa’s College and Thirumanagalam stations, concourse-level work is in progress in Washermenpet and Shenoy Nagar.

In the Anna Salai stretch (corridor I), where as many as seven stations are coming up from Saidapet to Government Estate, the placement of diaphragm wall panels is in progress in most of the stations.

When asked about a possible delay of work during the monsoon season this year and how they plan to tackle it, Mr. Somasundaram said CMRL had made arrangements to cover the openings and also pump out water in case of flooding inside the site.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.