Tantransco lines up projects to meet demand

The demand has touched 3,200 MW this year, testing the city’s ‘fragile’ transmission network

May 31, 2017 12:31 am | Updated 12:31 am IST - CHENNAI

The State’s power managers find the electricity demand in the city growing rapidly every year. The demand, which remained at a ‘manageable’ level of 3,000 MW till last year, has almost touched 3,200 MW this year, severely testing the city’s ‘fragile’ transmission network.

Though Tamil Nadu Generation and Distribution Company (Tangedco) is in a comfortable position with a generation capacity of more than 18,000 MW, the chronic lack of development in the transmission network has led to power failures on more than three occasions in the past two months.

Heavy demand this year

A senior Tangedco official said the city has seen a heavy surge in demand this summer because of air-conditioners being used almost constantly, though there has been an overall reduction in power demand in the State by 600 MW. The official said power cuts are occurring because of issues concerning transmission network, and they have already planned to sort these out by continuous infrastructure development work in the coming years.

The Tamil Nadu Transmission Corporation (Tantransco) has already started executing several power infrastructure projects of sub-stations and transmission lines. While work on 20 sub-stations of capacities of 400 KV, 230 KV, 110 KV and 33 KV, is in progress, Tantransco has lined up proposals for constructing more than 40 sub-stations to meet the demand in future. The official said Tantransco would be constructing new 400 KV sub-stations in Pulianthope, Guindy, Korattur and Taramani.

Big sub-stations

Similarly, six 230-KV and 15 110-KV capacity sub-stations have been proposed in different parts of the city.

In addition to these big sub-stations, 18 smaller type of 33-KV sub-stations are planned, which would help in better regulation of electricity supply. New 33-KV sub-stations are planned at Karambakkam, Ponniamman Nagar in Iyyappanthangal and Aminjikarai. The 43 sub-stations would be executed at a cost of ₹3,248 crore.

The official said: “The smaller sub-stations are needed as they play a vital part in preventing low voltage and give the option of backfeeding in case of any failure of feeder lines.”

Tantransco also has several pending tasks such as laying of underground electricity cable network, upgradation of sub-stations, enhancement of power transformers and renovation of old sub-stations.

The total budget outlay of ₹915.65 crore has been allotted for these projects.

Underground cables

The major underground cable network project involves installation of electricity cables between Sriperumbudur and Taramani at a cost of ₹289.70 crore and from Kalivanthapattu to Taramani at a cost ₹268.30 crore.

The official said there would be major relief to city residents once two major feeder lines, which were caught in some legal problems, to Ottiyambakkam in south Chennai and Manali in north Chennai, are completed.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.