Porur flyover likely to be opened in two weeks

475m facility was built over 7 years at a cost of ₹54 crore

May 14, 2017 07:08 am | Updated 07:08 am IST - CHENNAI

CHENNAI, TAMIL NADU, 13/05/2017, The Porur Flyover is nearing completion on Saturday. Photo: M. Vedhan.

CHENNAI, TAMIL NADU, 13/05/2017, The Porur Flyover is nearing completion on Saturday. Photo: M. Vedhan.

After seven years of work that went on in fits and starts, the Highways Department is giving the finishing touches to the ₹54 crore flyover at the Porur junction on Mount Poonamallee Road. It is expected to be ready in two weeks.

Work on the 475 metre long and 17.2 metre wide flyover that began in 2010 had to be put on hold when huge underground water mains came in the way. Though construction resumed in 2015, it progressed slowly due to the lack of permission for traffic diversion and work had to be carried out during late nights only.

Soil conditions

Many residents expressed relief at the work finally coming to an end. Settu, an autorickshaw driver in Devi Nagar, recalled that the project had to be put on hold due to the presence of water mains and the soil condition.

“On some days, it takes more than 45 minutes for us to travel from Sri Ramachandra Hospital to the other side of the flyover. Once the flyover is completed, it will be used by vehicles of school, colleges and IT companies, leading to a reduction in congestion,” he said, adding that Arcot Road too should be widened to allow free movement of traffic.

Traffic snarls are common on the road that leads to Sriperumbudur and beyond. Pedestrians too struggle to cross the road. “It takes up to 15 minutes before you can finally cross the road. A subway beneath the flyover and pedestrian crossings on the sides where it lands would help pedestrians,” said S. Sanathkumar, who works in a power tools repair shop on Mount Poonamallee Road.

A bus stop on the Poonamallee side is just at the point where the flyover lands. It has to be shifted to prevent traffic jams on the service lane, Mr. Sanathkumar added.

Sources in the Highways Department said the priority now is to complete the flyover.

“We had to deal with a huge bunch of telecom cables last month and that delayed the construction. Painting, electrification and laying of BT topping will be taken up soon,” an official said.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.