Drain first, widening later on Taramani Link Road

February 02, 2013 03:32 am | Updated 11:46 am IST - CHENNAI:

Work on the drain is expected to be completed by August. If delayed, motorists will have to endure a back-breaking commute during the monsoon, this year too — Photo: S.S. Kumar

Work on the drain is expected to be completed by August. If delayed, motorists will have to endure a back-breaking commute during the monsoon, this year too — Photo: S.S. Kumar

Work to widen and strengthen Taramani Link Road is expected to be completed this December.

The work was delayed because a drain being constructed on the road is yet to be completed.

On Friday, a team of officials from the World Bank suggested the installation of 15 precast slabs per day along the road, to speed up work on the drain. At present, the Public Works Department (PWD) is only installing 10 precast slabs per day.

The Chennai Metropolitan Development Authority (CMDA) has requested the PWD to ensure the drain is completed by August, so that work on widening the road can then begin.

The World Bank, which is funding the project, has already accepted CMDA’s request to extend the deadline for the completion of the project, originally scheduled to be finished in March 2011. The CMDA had first sought and received an extension until March 2012. This is the second extension it has sought.

Once widened and strengthened, the road will improve connectivity between Velachery and Rajiv Gandhi Salai.

The project is part of a comprehensive urban transportation initiative undertaken by the State government with World Bank assistance, under Third Tamil Nadu Urban Development Project (TNUDP-III).

Initially, the alignment of the drain, which is being built under the Jawaharlal Nehru Urban Renewal Mission was in conflict with the road-widening project. So the contract was cancelled and was then re-awarded, after the first contractor was unable to complete the project.

Improvement in the traffic and transportation sectors within the Chennai metropolitan area is one of the urban investment components covered under TNUDP III.

This component is coordinated by a project management unit of the CMDA.

While roads, bridges, grade separators and pedestrian subways are implemented through a project implementation unit of the State highways department, the traffic improvement programme comes under the city traffic police.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.