Public fed up as underpass construction drags on

January 14, 2012 09:27 am | Updated October 18, 2016 01:05 pm IST

The fourth wing of the pedestrian subway near K.R. Market that is being delayed. Photo: K. Bhagya Prakash

The fourth wing of the pedestrian subway near K.R. Market that is being delayed. Photo: K. Bhagya Prakash

K.R. Market is one of the busiest parts of the city. As the city's epicentre, it throngs with thousands of traders and farmers coming to sell their wares. Yet, there is little infrastructure for the citizens, right from public toilets to pedestrian underpasses/subways.

For the past six years, the construction of the pedestrian underpass at K.R. Market has dragged on. Of the four wings, three are ready. The remaining — K.R. Market to Apsara theatre (opposite Hotel Taj) — is still a long way off. Though not officially opened, people use the underpass wings that connect Vani Vilas Hospital, Jumma Masjid (near Chandra Bhavan) and K.R. Market.

Syed Sajjad, a resident of Kalasipalya, said he uses the underpass regularly. “It is a boon as thousands visit the K.R. Market area every day. However, one wing is yet to be opened. No one knows why the construction is being delayed.”

Another resident, Abdul Jabbar, suspected corruption.

Three years late

Dharmaraya temple councillor P. Dhanraj told The Hindu the Bruhat Bangalore Mahanagara Palike (BBMP) took up the construction at a cost of Rs. 6 crore in September 2006, and was to have completed it early 2009.

“A major bottleneck was the delay in the shifting of the sanitary line by the Bangalore Water Supply and Sewerage Board (BWSSB). The BWSSB gave an inflated estimate of Rs. 1.92 crore, when it should have been Rs. 64 lakh,” he said.

Left with no other alternative, the BBMP deposited Rs. 1.92 crore with the BWSSB. The contractor, Maruthi Constructions, was also to be blamed for the inordinate delay. “This included shifting of the line and restoration of the road. However, the BWSSB officials have failed to restore the stretch between Jumma Masjid and Bamboo Bazaar,” he added.

New promise

BBMP officials claim the construction would be complete by February-end. “Only the final link needs to be completed. For this, the traffic in front of Jumma Masjid (towards Hotel Taj) needs to be diverted. We have already requested the traffic police regarding the same,” an official said.

The pre-cast elements are all ready. “We just need to cut the road, place the pre-cast elements and align them. The work should be completed in a month.”

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.