Multiple agencies responsible for power outages, says Bescom MD

Staff Reporter
Comment (1)   ·   print   ·   T  T  
Bangalore is the only metro in India where power supply for the city is in the hands of three agencies in a series one after another, P. Manivannan’s post said. File photo: Bhagya Praksh K
Bangalore is the only metro in India where power supply for the city is in the hands of three agencies in a series one after another, P. Manivannan’s post said. File photo: Bhagya Praksh K

‘Capacity of receiving stations hasn’t kept up with city’s growth’

Faced with frequent power cuts? Blame too many agencies managing power generation, transmission and distribution. Bangalore Electricity Supply Company (Bescom) Managing Director P. Manivannan, in a late-night post on a social networking site on Monday explaining the two-day continuous power cuts that plagued parts of south Bangalore, has pointed to this being the reason.

“Bangalore is the only metro in India where power supply for the city is in the hands of three agencies in a series one after another. Electricity flows though three different companies before reaching your home. If any one of them fails, you don’t get the supply,” the post said.

Referring to power generation at the various plants such as the Raichur Thermal Power Station, transmission by the Karnataka Power Transmission Corporation Ltd., and distribution by Bescom, Mr. Manivannan has said that if one of them fails, it will affect power supply.

He also pointed out to the poor condition of the receiving stations for Bangalore — Peenya (for north), Hoodi (for east), and Somanahalli (for south). “All these three are in bad shape. They are overloaded, and increase in the consumption makes them trip. Their capacity is not augmented at the pace the city grew. One reason could be that, nobody wants to take a risk of creating more capacity.”

“The point is, should there be one single agency (generation, transmission and distribution) which should be accountable for power supply to the city like Bangalore?” the post added.

More In: Bangalore

This is where a System Operator(a Govt entity) has a role to play ..
A systems operator's job is not just to dispatch but to take
preventive action by foreseeing such problems..it has to be pro-
active..Bringing in synergy between the different gencos,transcos and
discos is also one of its responsibilities..It has to come up with
proper means for Congestion Management? and in extreme cases
augmentation of capacity..unfortunately augmentation of transmission
capacity is fraught with various problems like R.O.W etc.but that is
still the ultimate solution for rampant congestion and resulting
outages..it is strange that the govt has not yet taken steps for
transmission capacity augmentation..it's high time that the SO reads
these signals and proposes an augmentation of capacity..

from:  Tulika
Posted on: Apr 25, 2013 at 11:43 IST
This article is closed for comments.
Please Email the Editor

Bangalore Connect Newsfeed

Karnataka

Mangalore


O
P
E
N

close

Recent Article in Bangalore

Betterment benefit extended to unapproved layouts

There is some good news for citizens who own revenue sites and sites in layouts that have not been approved by any planning authority. T... »