BMRCL sticks to April 2017 date for Phase I completion

Trials on elevated stretch of south line to be done on one set of tracks for now

November 21, 2016 07:28 am | Updated August 29, 2019 10:33 am IST - Bengaluru

KARNATAKA - BENGALURU - 20/11/2016 :  Green line Namma Metro Train arriving at National College station for the first time on the southern side on the city, since the completion of the elevated sections of the metro lines through South Bengaluru was completed (Green Line between Kempegowda station and National College), a train has rolled on its tracks, in Bengaluru on November 20, 2016. A day ahead of the launch of trials on the South Line (Green Line), Bangalore Metro Rail Corporation Limited (BMRCL) officials successfully managed to push a train through from Sampige Road Metro Station then to the yet-to-be-completed underground stations of Chikpete and K.R. Market on the North-South line towards National College station. The South Line between National College and Yelachenahalli has been lying idle for over two years. BMRCL could not start services or conduct trials on this line as the only depot was located at Peenya, and the crucial underground stretches had not yet been completed. Trials are expected to go on till March next year before operations begin in April on this stretch.   Photo: K. Murali Kumar.

KARNATAKA - BENGALURU - 20/11/2016 : Green line Namma Metro Train arriving at National College station for the first time on the southern side on the city, since the completion of the elevated sections of the metro lines through South Bengaluru was completed (Green Line between Kempegowda station and National College), a train has rolled on its tracks, in Bengaluru on November 20, 2016. A day ahead of the launch of trials on the South Line (Green Line), Bangalore Metro Rail Corporation Limited (BMRCL) officials successfully managed to push a train through from Sampige Road Metro Station then to the yet-to-be-completed underground stations of Chikpete and K.R. Market on the North-South line towards National College station. The South Line between National College and Yelachenahalli has been lying idle for over two years. BMRCL could not start services or conduct trials on this line as the only depot was located at Peenya, and the crucial underground stretches had not yet been completed. Trials are expected to go on till March next year before operations begin in April on this stretch. Photo: K. Murali Kumar.

Can commuters from Nagasandra in Bengaluru north zip in a metro towards Puttenahalli on the southern end of the city in a matter of 45 minutes from April 2017?

Despite scepticism over assurances of Bangalore Metro Rail Corporation Ltd. (BMRCL) — which has missed several deadlines — officials are confident that the whole Phase I of the metro network can be thrown open by mid-2017.

In the coming days, for the first time, a train will roll along the 8 km of the elevated sections between National College and Yelachenahalli (Puttenahalli), said BMRCL managing director Pradeep Singh Kharola.

“Preparations have been going for a week now, and a motor-trolley test of nearly five hours has been conducted. A battery-powered locomotive has been pushed through the underground stretch. It took 20 hours with more than 400 engineers to get the train to the elevated sections,” said Mr. Kharola after a symbolic programme to mark the start of the trials on Sunday.

However, trials can now be done only on one set of tracks (towards Yelachenahalli). A train cannot be pushed through on the other side as the underground tunnel (between K.R. Market and Kempegowda interchange ) is yet to be completed.

“Laying of tracks has been done in this tunnel, and work on cabling, tunnel ventilation and signalling are still going on. We hope to complete this by December-end,” said Mr. Kharola.

Once tests are completed, the Commissioner for Railway Safety (CRS) will be called for final approval after which commercial operations can start. Bengaluru Development Minister K.J. George said this process was expected to be completed around April 2017.

It has been more than two years since civil works on eight stations (Reach 4 and 4a) had been completed, but trials could not commence as there was difficulty pushing a train onto the track (tunnelling on the underground stretch at Chikpete had seen severe delays).

Jayanagar MLA B.N. Vijaykumar said the opening of the section would go a long way to decongest areas along the crucial metro line.

Challenges

The vast scope of the trials — where data running into lakhs of pages are collected — implies that deadlines are hard to fix. For the now-operational underground sections of the Purple Line, the first train rolled in March 2015. However, commercial operations began only a year later. For the elevated stretch of Mysuru Road to Magadi Road, the line was thrown open nearly eight months after trials began.

Phase II by 2020: BMRCL

Bangalore Metro Rail Corporation Ltd. (BMRCL) believes the elevated extensions as a part of the Phase II — which will add 33 km to the existing network — of the Namma Metro can be completed by 2020.

Work on 8-km extension from Mysuru Road to Kengeri as well as the 6.29-km extension from Yelachenahalli to Anjapaura on Kanakapura Road is in progress and will be complete by mid-2018. “Land acquisition for the (15.5-km) Baiyappanahalli – Whitefield extension has been almost completed and tenders will be floated early next year. Considering around three years for construction and trials, this line should be operational from 2020,” said Pradeep Singh Kharola, managing director, BMRCL.

Green Line

Nearly 12-km of metro network from Sampige Road Station to Yelachenahalli is yet to be thrown open

It has 14 stations, including three underground ones

This is part of 24-km line from Nagasandra to Yelachenahalli

Expected travel time is 45 minutes

Cost of elevated stretch (eight stations): Rs. 627 crore

Currently, one underground tunnel from Sampige Road towards Yelachenahalli is functional

Other line expected to be completed by December-end

99 per cent of the civil construction was completed in 2014

In October 2015, BMRCL considered lifting trains to elevated sections. Idea was later dropped owing to financial infeasibility

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.