Work on lift irrigation scheme at brisk pace, says Konathala

Partial completion of Phase I of Purushothapatnam project is likely by August

May 10, 2017 08:12 am | Updated 08:12 am IST - VISAKHAPATNAM

Work going on at Purushottapatnam Lift Scheme in East Godavari district.

Work going on at Purushottapatnam Lift Scheme in East Godavari district.

A team of the Uttarandhra Projectla Sadhana Samiti that visited the headworks of the Purushothapatnam Lift Irrigation scheme on the Godavari on Tuesday is happy with the brisk pace of work.

It is of the view that the Phase I could not be completed by August as planned by the State government but could be partially completed.

Huge benefit seen

“However, Phase I will be ready by the next summer so as to meet the water needs of Visakhapatnam. It will also hugely benefit farmers in East Godavari district by stabilising irrigation for 2.5 lakh acres,” said former Minister Konathala Ramakrishna, a member of the samiti.

Others who visited the work included former Government Whip Dronamraju Srinivasa Rao, Irrigation Advisor to the Government and retired Chief Engineer S. Satyanarayana, former Superintending Engineer Brahmanaiah, CPI district secretary A.J. Stalin, former Chairman of the Zilla Grandhalaya Samstha Thota Nagesh and Uttarandhra Rakshana Vedika President S. Siva Sankar.

Ten motors had to be fixed at the lift scheme and some of them could be ready by August, Mr. Ramakrishna said. Water would be lifted from Purushothapatnam into the Left Main Canal of the Polavaram multi-purpose project 10 km away. In the first phase, a regulator would be constructed at Yeleru to pump water into the Yeleru reservoir. The cost of the scheme is ₹1,551 crore.

The former Minister said about 6 km of the pipeline work at Purushothapatnam was completed and the work at Yeleru had also begun.

However, tenders had been called for the two crossings on the national highway and were yet to be finalised. Mr. Ramakrishna said at least for 50,000 acres in the Payakaraopeta constituency under the Polavaram LMC irrigation should be provided in the first phase.

Besides work on the LMC was not going on in a full-fledged manner in the eight packages and was brisk in only one or two packages. It should be expedited and simultaneously tanks for storage of the LMC water readied.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.