RINL to complete capital repairs to blast furnace in 135 days

November 08, 2013 12:51 pm | Updated 12:51 pm IST - VISAKHAPATNAM:

Buoyed by the successful tapping of ‘first heat’ from the New Steel Melt Shop-2 marking the completion of Rs.12,500-crore 6.3 million tonne expansion, Rashtriya Ispat Nigam Limited has undertaken the capital repairs of Blast Furnace Godavari to increase production by half a million tonnes.

RINL Chairman-cum-Managing Director A.P. Choudhary congratulated the Projects and Works Collective, the various equipment suppliers, civil and structural contractors for launching hot metal production from SMS-2 and appreciated the efforts put in by all of them for rolling out finished products shortly with the commissioning state-of-the-art Wire Rod Mill.

After achieving a throughput of 37.74 million tonne of hot metal on carbon lining in a campaign life of 23 years, the Blast Furnace-1 Godavari was successfully blown out recently for Category-1 capital repairs.

The capital repairs would take 135 days and the modernisation of the furnace would enhance the production by 0.5 million tonne with the increase in volume from the present 3200 cum to 3800 cum, an RINL spokesman said.

RINL surpassed the sales target by achieving a turnover of Rs. 6,807 crore during April-October, 2013 compared to corresponding period last year (CPLY) of Rs. 6,736 crore.

The sales turnover of Rs. 1,033 crore in October represents a growth of 7 per cent over CPLY. Iron and steel sales during the period recorded a growth of 11 per cent.

Captive power generation

The Navratna company received a shot in the arm with the commissioning of 67.5 MW Turbo Generator No.5 put up by BHEL at Visakhapatnam Steel Plant on Wednesday.

The total cost of the plant including civil, structural and auxiliary works is around Rs.343 crore.

The commissioning of Turbo Generator-5 will enable VSP to meet part of its captive need including emergency requirement of the expansion plant.

RINL Directors Umesh Chandra (Operations), P.C. Mohapatra (Projects) and Executive Director (Works) R. Ranjan (Works) and others were present.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.