Temple works get delayed

Contractors reluctant to complete works as revised estimates are not approved

July 26, 2013 01:09 pm | Updated October 26, 2016 03:54 pm IST - VIJAYAWADA:

A view of Mallikarjuna Mahamandpam  being constructed by Sri Durga Malleswara Swamyvarla Devasthanam in Vijayawada. Photo: V. Raju

A view of Mallikarjuna Mahamandpam being constructed by Sri Durga Malleswara Swamyvarla Devasthanam in Vijayawada. Photo: V. Raju

The work on Rajagopuram and Mallikarjuna Mahamandpam has come to a grinding halt due to delay in approval of revised estimates by the State government.

The contractors have virtually stopped the works under the garb that the revised estimates are not approved.

Sri Durga Malleswara Swamvarla Devasthanam authorities have sent the revised estimates to the government for its approval some time ago. The temple authorities initially estimated that the Rajagopuram would cost Rs.9.8 crore. Later, it was estimated that it would cost between Rs. 15 crore and Rs.16 crore.

Likewise, the cost of the Mahamandapam was estimated at Rs. 20.5 crore initially, and now it has escalated to Rs. 22.5 crore. The contractors fear the temple might not be able to clear the bills if the government does not approve the revised estimates.

There is an escalation of 8 to 10 per cent in the cost of the two projects for various reasons, including change and approval of designs, sand scarcity, non-availability of skilled labour (for the Rajagopuram). Still uncertainty looms over the ramps for the Mahamandapam though the officials are confident that the Mahamandapam would be constructed as per original design. The government is yet to sanction permission to the ramps, according to sources.

Divergent views

There are divergent views on construction of the ramps. While some oppose it, a few others favour it. Therefore, the department has constituted the committee to study the feasibility and requirement of the ramps. As per the original design, two ramps – exit and entry – would be part of the mandapam. It is estimated that the entry ramp would cost Rs. 8.2 crore and exit ramp Rs. 3.2 crore.

The two structures are unlikely to be complete before Dasara if pace of the work is any indication. The temple authorities have failed to complete the construction of the Mahamandapam by December 2011 as was announced. The temple authorities commenced the works in June 2009, and announced that the mahamandapam would be completed for 2010 Dasara.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.