No solution in sight for Jakkampudi STP

Though the Railways has given permission, the VMC has no funds

August 02, 2012 01:25 pm | Updated November 16, 2021 11:17 pm IST - VIJAYAWADA

A view of Sewerage Treatment  Plant (STP), which is being constructed under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) programme at Jakkampudi near Vijayawada, is badly hit due to paucity of funds. Photo: Ch.Vijaya Bhaskar

A view of Sewerage Treatment Plant (STP), which is being constructed under Jawaharlal Nehru National Urban Renewal Mission (JNNURM) programme at Jakkampudi near Vijayawada, is badly hit due to paucity of funds. Photo: Ch.Vijaya Bhaskar

The Railways has given its consent for laying a pipeline for carrying sewer under its railway tracks at Jakkampudi near here. But the Vijayawada Municipal Corporation is clueless as to how to go about funding the project.

The Railways has asked the corporation to pay Rs. 6.5 crore towards according permission. The VMC has put the cost of laying the pipeline at Rs. 6 crore. So, the cost of construction and railway fee would take the total expenditure to more than Rs. 12 crore, sending the officials into a tizzy. The corporation officials have been running from pillar to post to get the permission from the Railways ever since the STP works began.

The railway fee is more than what the corporation would incur for laying the pipeline that would carry the sewer from One Town to a sewerage treatment plant being constructed at Jakkampudi. The STP would also cater to the needs of a housing complex constructed under the JNNURM for the shelterless, officials say.

The corporation has asked the Railways to have a re-look into the matter as it has constructed the houses for the poor.

Railway officials, however, said that the fee cannot be negotiated as it was calculated based on the laid down procedure and approved by the Railway Board.

The VMC has constructed 8,800 houses under the JNNURM to rehabilitate people living in vulnerable places like road margins, canal bunds, and riverbed. The sewer generated from the Jakampudi housing complex has no other outlet unless the STP is constructed. The sewer would have to be let into the Budameru without treating it.

The corporation, likewise, has planned to treat the sewerage generated in One Town to treat at the STP. The corporation is constructing two STPs with a capacity of 20 MLD each at Jakkampudi; while one is nearing completion, only 15 per cent of works on second STP were completed.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.