Tiruchi-Dindigul track doubling taken up on two stretches

80 minor bridges constructed on the two sections

December 04, 2013 12:33 pm | Updated 12:33 pm IST - TIRUCHI:

The Rail Vikas Nigam Limited (RVNL) has taken up track doubling works on two stretches beyond Tiruchi as part of the ongoing doubling project from Villupuram to Dindigul.

Works are under way in the nearly 25-km stretch from Manapparai to Kolathur and in the portion from Dindigul to Vadamadurai (16 km).

The RVNL, a special purpose vehicle and a wholly owned government company, is executing the doubling project in different portions in the 270 km section from Villupuram to Dindigul at a cost of around Rs. 1,200 crore.

Railway officials said the track linking works in the Manapparai – Kolathur and Dindigul – Vadamadurai stretches had commenced following completion of earthwork and construction of new bridges.

About 80 minor bridges had been constructed in both portions with loco trials on the newly laid second track expected to be done before March.

The organisation would approach the district administration authorities seeking land that was required for executing the project, said an official.

A new station building would be constructed at Kalpattichatram between Manapparai and Dindigul Junction while additional buildings would come up in the existing stations falling within the two stretches.

The officials said the ongoing track doubling work in the 25-km portion from Kallakudi Palanganatham to Ariyalur, falling in the Tiruchi–Ariyalur BG section, was apace.

New station buildings have been constructed at Kallagam and Sillakudi and doubling works were expected to be completed by February after which the Commissioner of Railway Safety (CRS) would be invited to inspect the second track.

The RVNL had commissioned the double line between Valadi and Kallakudi Palanganatham (25 km) in July upon obtaining the mandatory clearance from the CRS.

The organisation had taken up doubling work in the Valadi–Kallakudi Palanganatham–Ariyalur (50 km) portion on priority as it was a crucial segment in the Villupuram–Tiruchi chord line section and to reduce congestion especially at night.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.