UPCL issues may be resolved in two weeks

State Cabinet is likely to take it up to speed up commissioning of second unit

May 07, 2012 04:17 pm | Updated October 18, 2016 01:05 pm IST - MANGALORE

The State Government will give priority to resolve issues that were delaying in commissioning the second unit of the Udupi Power Corporation's coal-based power plant. The Cabinet will be taking up the matter shortly and resolve the issues in the next two weeks, said Chief Minister D.V. Sadananda Gowda.

Mr. Gowda told presspersons here on Sunday that there had been several reasons for the delay. There was delay on the part of the company at the time of construction of power plants because of failure of Chinese engineers to attend the work following earthquake in China. There had been delay because of the change in the stand of Indonesia over supply of coal, he said.

On the other hand, getting clearance from the Ministry of Environment and Forest was delayed for the Karnataka Power Transmission Corporation's work of setting up the 400 kV transmission line for evacuating power from the project. “There are other problems too. There is also environment problem,” he said.

Mr. Gowda said the State Government had taken a serious view of the project. In the coming Cabinet meeting, discussions would be held about memorandum of understanding to be signed by the UPCL, the Government, and the Electricity Supply Companies. “We will take steps to resolve all issues in the next two weeks,” he said.

The 1200 MW coal-based power plant of the UPCL was located in the Nanidkur village near Udupi. While the first unit of the plant of 600 MW capacity started commercial operations in November 2010, the second unit, also with a capacity of 600 MW, was yet to begin its operations.

A few days ago, T.V. Ramachandra from Energy and Wetlands Research Group of the Indian Institute of Science, Bangalore, and Y.B. Ramakrishna, Executive Chairman of Karnataka State Biofuel Development Board, submitted to Vishwesha Tirtha Swami of Pejawar Mathi, a detailed report about the problems caused because of UPCL.

The swamiji demanded the State Government take steps to stop pollution or shut down the plant's operation.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.