People can link sewer lines to drainage system in two months

10 members are checking the network in phases before allowing house connections

November 16, 2015 12:00 am | Updated 05:37 am IST - MANGALURU:

More than a year after a 160-km long underground sewer network in Jeppinamogaru and Surathkal is ready, the Mangaluru City Corporation (MCC) has now decided to allow people to provide house connection.

According to H.N. Gopalakrishna, commissioner of the corporation, people will be allowed to link their houses’ sewer lines to the manholes in the network within two months in phases.

Of the 160-km network, 65-km sewer line from Shivabagh, Maroli, Tarethota, Pumpwell, Yekkur, Jeppinamogaru, Bajal and surrounding areas was connected to the sewage treatment plant (STP) at Jeppinamogaru with a processing capacity of 20 million litres a day (MLD).

Another 90-km long underground pipelines from Hosabettu, Kulai, Katipalla and Surathkal were connected to the 16.5 MLD capacity STP at Surathkal.

Deepak K. Poojary, chairman, Standing Committee for Town Planning and Improvement, said that people in Shivbagh would be allowed to provide house connection. Later, it would be allowed in other areas like Maroli, Tarethota and remaining places where the network are connected to the STP at Jeppinamogaru.

He said that 10 members was now checking the network in phases before allowing the house connections.

Mr. Poojary said that now the electricity connection to the STP at Surathkal was under trial. People in its surroundings would also be allowed to provide house connection within two months.

Referring to missing pipeline links in the network in some places he said that they would be addressed simultaneously.

The first priority was to allow people in areas where no missing links have been found to allow house connection, he said.

A recent survey by MCC officials had found some loose ends in the sewer project implemented by Karnataka Urban Infrastructure Development and Finance Corporation (KUIDFC) for the MCC. It found missing links of main sewer lines at 25 places. In addition, there were issues relating to laying connecting roads, railway and constructing retaining walls and repair of manholes.

The missing links was due to issues relating to availability of land, court issues and rock formation in the sites coming in the way of linking pipelines.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.