New vented dam at Thumbe may be ready by 2013

Height of the dam raised, cost escalates to Rs. 79.50 crore

February 22, 2012 02:36 pm | Updated November 17, 2021 12:18 am IST - MANGALORE:

The new vented dam across the Netravathi at Thumbe is expected to be ready by the end of 2013, according to L.N. Anand, Executive Engineer, Karnataka Urban Water Supply and Drainage Board (KUWSDB), Mangalore.

Speaking to presspersons at Thumbe on Tuesday on the sidelines of Ganga Pooja to the river organised by Mangalore City Corporation, Mr. Anand said that 25 per cent of the construction work had been completed.

The work was started in 2010 and the cost now has escalated to Rs. 79.50 crore as against the earlier estimate of Rs. 40 crore.

Mr. Anand, who is supervising the construction work, cited four reasons for the cost escalation. The height and depth of the dam is now being increased.

Use of quality grade concrete and the higher premium quoted by the contractor have contributed to the cost escalation. The tendered amount stood at Rs. 48.21 crore.

The Executive Engineer said the height of the dam would be increased from 10 metres to 12 metres to make it flood-resistant. The maximum flood water level recorded in Thumbe was 11.79 metres in 1974.

He said the maximum storage level at the dam would be seven metres with a storage capacity of 14.75 million cubic metres as against the existing 4.89 million cubic metres. Even if there was zero inflow, the city could be provided uninterrupted water supply for five months.

He said the new dam would have electrically operated mechanical gates.

Advisor

He said the KUWSDB was seeking the advice of Sankappa Shetty, retired Chief Engineer, Karnataka Power Corporation Ltd. (KPCL) while building the dam. Its foundation structure was being inspected and certified by the geologists (of General Manager level) of the KPCL at regular intervals. Quality of construction was being inspected by the authorities of Indian Register of Shipping which was the third party inspecting agency.

Tor Steel Research Foundation in India had designed the dam. Rithwik Projects Ltd. and Swapna Constructions (Joint Venture) of Hyderabad was building the dam.

When water was stored in the new dam, 69.48 hectare of revenue land and 364.29 hectares of river area would be submerged.

Mayor Praveen and Deputy Mayor Geetha Nayak performed Ganga puja. The Commissioner of the corporation Harish Kumar K. was present.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.