Crores of rupees go down the sea wall in Ullal

Rs. 12 crore has been spent since 2001 on building temporary sea walls

August 07, 2013 10:23 am | Updated November 17, 2021 01:33 am IST - Mangalore:

Work under way on building the boundaries of the sea wall at Yerumal in Mangalore. Photo: R. Eswarraj

Work under way on building the boundaries of the sea wall at Yerumal in Mangalore. Photo: R. Eswarraj

Every year it’s the same tale: the monsoon breeze whips the sea into a frenzy, which in turn takes out its anger on the coast, sweeping down roads and houses; and after a few days of damage, the district administration announces funds for temporary sea walls. Stones are dumped, and by the time the waves pound the shores again next year, the stones have seemingly reduced in competency.

Including the Rs. 1.43 crore allotted for temporary sea wall construction this year, over Rs. 12 crore has been spent, almost like a yearly ritual, since 2001 — a majority of which is spent in and around Ullal.

As reported numerous times, during sea erosion, residents of Mogaveerpatna, Mukacherry and other areas complain of the inadequacy of the temporary walls, or that the walls are strengthened and augmented only after considerable damage has been done.

Even engineers at the Ports Department are baffled by the fast disappearance of the walls.

“We don’t expect sea erosion around 1.5 metres below the sea surface; but it happens here. As the sand beneath the wall is being taken away, the wall sinks and rocks are washed away,” said an engineer, adding that hurried nature of the wall construction expedites the process.

Even so, with names like Hilarinagar, Subashnagar, Mogaveerapatna routinely popping up in emergency works, why can’t the department plan before the advent of the monsoon?

“We can’t predict where sea erosion will happen…and we will dump stones only when it seems essential,” said A.S. Rao, Assistant Executive Engineer, adding that erosion had intensified since the construction of breakwaters at the old and new ports here.

He claimed that works are expedited by breaking them into smaller sections that cost less than Rs. 2.5 lakh each (thereby, bypassing government regulations regarding issuing of tenders), while contractors are “contacted informally”.

Unpaid bills

However, in 2010, this led to procedural trouble, and payment was withheld. In the two subsequent years, even with reports of sea erosion, works were not taken up as contractors refused to come forward until payment was done. Though payment was approved this year, considerable damage had been done already.

Even engineers in the department are sceptical of the hurried-nature of the sea walls — something they say is dictated by political pressure instead of scientific survey. Moreover, they question the quality of work as the “same contractors, who come forward, have formed a lobby”.

Hindrance

While denying the presence of a lobby, a contractor said trouble in getting stones, areas with no approach roads, and rough seas hindered the work. “A temporary sea wall here can last only a year, and we can’t do much about it,” he claimed.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.