Pachalam overbridge: From file to pile, in just 5 days

Pachalam overbridge works begin within one week of Cabinet sanction

March 05, 2014 11:17 am | Updated May 19, 2016 06:25 am IST - KOCHI:

People’s representatives are all ears as DMRC’s E. Sreedharan explains the details of piling that began on Tuesday for Pachalam overbridge. The bridge is expected to be up in 6 months. Photo: Vipin Chandran

People’s representatives are all ears as DMRC’s E. Sreedharan explains the details of piling that began on Tuesday for Pachalam overbridge. The bridge is expected to be up in 6 months. Photo: Vipin Chandran

It took just five days for Pachalam overbridge works to get off the blocks from the day it got the Cabinet go-ahead.

On Tuesday, piling began for the two-lane road overbridge for which Rs. 52 crore has been sanctioned. The project cost includes the money that has to be shelled out to acquire 46 cents of land.

The Delhi Metro Rail Corporation has scheduled to commission the bridge within six months of handing over the acquired land.

At the inaugural, Union Minister of State K.V. Thomas said: “The speed at which Kochi Metro Rail Limited’s MD Elias George catalysed ‘file movement’ and DMRC Principal Advisor E. Sreedharan’s insistence that work must begin the very same day the foundation stone is laid augur well for the bridge. Mr. Sreedharan has said the bridge will be built in such a way that it can be four laned at a later stage”.

“Next in line is construction of a bridge at Vaduthala, which DMRC must undertake. Widening of extremely narrow roads in the locality is another priority,” he said. Following criticism that the foundation stone was laid before a Government Order was issued, a GO was issued by Tuesday evening.

P Rajeeve, MP, blamed successive governments for failing to four lane NH 47 and NH 17 despite acquiring land at 30-metre width three decades ago. Charles Dias, MP, and MLAs from the district were among those present.

Traders’ protest

A section of traders protested against the launching of the overbridge project late on Tuesday night.They staged the protested after workers of the DMRC blocked the thoroughfare in the area. Sources said traffic regulations will be in place at Pachalam level crossing till the bridge is ready.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.