Metro work disrupted in Kalamassery

Officials with the Delhi Metro Rail Corporation said the project had come to a complete standstill near the dumping yard in Kalamassery with the municipality directing metro to stop all activities till further intimation.

April 25, 2014 10:24 am | Updated May 21, 2016 01:19 pm IST - KOCHI

Kalamassery Municipality said they took the step following repeated violations by the metro authority regarding the agreement on land use and related issues. Photo: K. K. Mustafah

Kalamassery Municipality said they took the step following repeated violations by the metro authority regarding the agreement on land use and related issues. Photo: K. K. Mustafah

Even as attempts are on to speed up its progress, the Kochi metro rail project has run into another blockade in the form of a ban on works from the Kalamassery municipality.

Officials with the Delhi Metro Rail Corporation said the project had come to a complete standstill near the dumping yard in Kalamassery with the municipality directing metro to stop all activities till further intimation. “Following this, works on the six piers from 218 to 223, have been held up from April 13 onwards, breaking the momentum of works between Aluva and Palarivattom,” they said.

"There is a need to complete the piers at the location, a low-lying area, before the onset of monsoon and any further delay in resuming the works would drag the schedule by another couple of months,” they warned.

Confirming the stoppage of works, officials at the Kalamassery Municipality said they took the step following repeated violations by the metro authority regarding the agreement on land use and related issues. “Ever since the works began in the area, they have been executing the works and traffic diversion plans on their own, without consulting us,” they said.

About three months ago, the municipality had served a letter to the metro rail authorities seeking urgent action to address the frequent bursting of water pipes and break of telephone networks due to the excavation work for the project. The agency, however, sat on the letter for a long period and came up for a dialogue only after we threatened to stop the work, they alleged.

On the occasion, they also accused the contractor agency of taking over more land than allotted for the metro works and dumping concrete waste in the area without permission.

Officials of the Kochi Metro Rail Limited informed that its Managing Director Elias George was scheduled to meet the municipality authority on April 26 to sort out all the outstanding issues.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.