MMTS phase II works back on track

Officials confident of the works being completed on time. Phase II of MMTS will enhance connectivity between Ghatkesar and Sanathnagar via Moula Ali (37 km), Bolarum-Medchal (14 km), Falaknuma-Umdanagar (14 km).

November 25, 2014 11:26 pm | Updated June 07, 2016 09:43 am IST - HYDERABAD:

Having lost steam earlier this year when they faced the threat of being shelved, MMTS phase II works are back on track, with officials optimistic about their completion on time.

Phase II was originally scheduled to start this January but was delayed when one of the partners pulled out from the joint venture. Rail Vikas Nigam Limited (RVNL), the Indian Railways arm entrusted with the project’s execution, roped in GMR Infra and Tata Projects to join existing partner Kalindee Nirman. Since August when works began, nearly one lakh cubic metres of earth work has been completed.

20 new bridges

“Phase II works are happening between Moula Ali and Sanathnagar, and Ghatkesar-Cherlapalli. At 20 locations, bridge works, including construction of new bridges, is progressing,” said RVNL chief project manager P. Srinivas.

Phase II of MMTS will enhance connectivity between Ghatkesar and Sanathnagar via Moula Ali (37 km), Bolarum-Medchal (14 km), Falaknuma-Umdanagar (14 km). The connectivity from Moula Ali to Sanathnagar will bypass Secunderabad station, providing the much needed relief to commuters during peak hours.

Phase II will also see five new railway stations come up between Sanathnagar and Moula Ali. A new rail line will be laid between Tellapur and Ramachandrapuram (4.5 km) and the existing railway line between Secunderabad and Bolarum, which is not electrified, will be electrified under the Rs. 819 crore phase II project.

Rs 60 cr. this year for project

Mr. Srinivas informed that Rs. 60 crore has been earmarked this financial year for the project, which will receive two-third funding from the State and the remainder from the Centre.

RVNL and South Central Railway (SCR) officials are optimistic of completing works phase II works within three years. Under phase I of MMTS, SCR currently runs 121 services transporting 1.5 lakh people on a daily basis. When completed, phase I and II will cater to five lakh passengers daily, said an official.

Improving transport

Phase II works happening between Moula Ali and Sanathnagar and Ghatkesar-Cherlapalli

Ghatkesar-Sanathnagar, Bolarum-Medchal, Falaknuma-Umdanagar connectivity to get boost

New rail line to be laid between Tellapur and Ramachandrapuram (4.5 km)

Railway line between Secunderabad and Bolarum, which is not electrified, will be electrified

MMTS phase I and II to cater to five lakh passengers daily, says official

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.