Conversion of grants into loans cautioned

Delay in completion of 5 irrigation projects taken up in 2005 could cost Telangana government dearly

March 28, 2017 01:45 am | Updated 01:45 am IST - HYDERABAD

The State government of united Andhra Pradesh received flak from the Comptroller and Auditor General (CAG) for several shortcomings in design, planning, survey and investigation, execution, and delay in completion of five medium irrigation projects taken up in 2005.

Though the projects were targeted to be completed within two years, only two — the Mathadivagu and the Ralivagu projects — were completed except for some ancillary work, while the remaining three were still under constriction even 11 years after they were first taken up, the CAG said in its audit report for 2015-2016, which was tabled in the Assembly on Monday.

“The projects were not completed due to improper planning, delay in submission and approval of design, rehabilitation and resettlement activities, and obtaining forest clearances, among other reasons. Irrigation potential of only 13,900 acres was achieved till May 2016 against the targeted 52,000 acres,” the report observed.

Despite receiving almost full grants under the Accelerated Irrigation Benefit Programme (AIBP), three projects — Gollavagu, Neelwai, and Peddavagu at Jagannathapur — were yet to be completed even after 11 years. The report pointed out that there was shortfall in utilisation of AIBP funds in respect to Gollavagu (₹2.24 crore) and Peddavagu (₹41.53 crore).

Survey delayed

“Since none of the projects were completed within the time stipulated by the AIBP, the possibility of conversion of grants to loans cannot be ruled out,” the CAG report cautioned the State government. It further pointed out that the projects were planned without properly taking into account water availability and planning village-wise irrigation potential. Survey and investigation activities were deficient and delayed. The delay on account of taking up relief and rehabilitation activities led to grant of extension of time to agencies.

Faulting the government for allowing undue benefits to work agencies, the CAG report stated that there were several such instances with changes in basic parameters or owing of agencies’ liabilities by the department. Drinking water facilities were not provided under any of the projects, as envisaged in the detailed project reports.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.