Herculean task before civic body in completing UGD works

Works related to scheme resulted in bad roads: residents

July 15, 2013 12:49 pm | Updated July 13, 2016 02:01 pm IST - SALEM

After terminating the contract with the private firm for failing to carry out the underground drainage (UGD) works as per schedule, the Corporation now has a Herculean task to look for a new contractor and resume work at the earliest and thereby put an end to the woes of the residents.

Corporation engineers said that though financial loss due to the current scenario can be manageable, the process of restarting the work involves cumbersome documentation and clearance at many levels at various departments of the State government. They added that the incomplete work in laying pipelines, giving house connections and relaying of tar-topped roads was posing a hardship to the residents as they had to encounter with bad roads everyday.

Engineers said that the entire process from preparing the revised estimate, getting administrative sanction from the government and the technical committee and finally placing the tender and inviting bids would take at least four months. Besides, selecting the contractor and executing the work would take another two months as a team of engineers had to carry out the entire process for resuming the work.

Members of various residential associations pointed out the difficulties they faced due to poor roads now and how the situation worsened during rainy season. Battling with bad roads was a tough and risky job everyday for residents and wanted relaying of road work to resume immediately.

The UGD work was initiated at a total cost of Rs. 149.39 crore with the State government grant of Rs. 10 crore, contribution from the corporation and from the public estimated at Rs. 78.85 crore and loan from Tamil Nadu Urban Development Fund III at 60.54 crore.

The entire work was divided into three packages, i.e, Package I at a cost of Rs. 15.50 crore to cover 86.14 km and the work order given on March 18, 2010, Package II at a cost of Rs. 37.70 crore to cover 150.65 km and the work order given on December 2, 2010 and Package III at a cost of Rs. 37.40 crore to cover 184.82 k.m. and the work order given on March 18, 2010.

The work order for Packages I and III of the UGD was terminated by the civic body recently, while work was in progress under Package II.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.