Reliance Power’s Sasan UMPP fully operational

March 30, 2015 05:13 pm | Updated 05:13 pm IST - MUMBAI

Anil Ambani controlled Reliance Power Ltd has announced the commissioning of the sixth and last 660 MW unit of the 3,960 MW Sasan Ultra Mega Power Project (UMPP).

With this, all the six units of Sasan UMPP have been commissioned 12 months ahead of Power Purchase Agreement (PPA) schedule, the company said on Monday.

The Sasan UMPP is the largest integrated power plant cum coal mining project at a single location involving investment of over Rs. 27,000 crore.

With this unit, Reliance Power’s generation capacity has increased to 5,945 MW which includes 5,760 MW of thermal and 185 MW of renewable energy based capacity.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.